7 Gas connections (continued)

Installation & Operation Manual

￿WARNING

￿WARNING

￿WARNING

Failure to apply pipe sealing compound as detailed in this manual can result in severe personal injury, death, or substantial property damage.

Knight wall mount boilers are typically shipped ready to fire on natural gas. Check boiler rating plate to determine which fuel the boiler is set for. If set to natural gas, it may be converted to LP by installing an orifice (see page 13). In order to operate on LP gas, an orifice MUST BE installed. Failure to comply could result in severe personal injury, death, or substantial property damage.

Use two wrenches when tightening gas piping at boiler (FIG. 7-2), using one wrench to prevent the boiler gas line connection from turning. Failure to support the boiler gas connection pipe to prevent it from turning could damage gas line components.

Natural gas:

Pipe sizing for natural gas

1.Refer to Table 7A for pipe length and diameter. Based on rated boiler input (divide by 1,000 to obtain cubic feet per hour).

a.Table 7A is only for natural gas with specific gravity 0.60 inches, with a pressure drop through the gas piping of 0.5 inches w.c.

b.For additional gas pipe sizing information, refer to ANSI Z223.1 (or B149.1 for Canadian installations).

Natural gas supply pressure requirements

1.Pressure required at the gas valve inlet pressure port:

Maximum 14 inches w.c. with no flow (lockup) or with boiler on.

Minimum 4 inches w.c. with gas flowing (verify during boiler startup).

2.Install 100% lockup gas pressure regulator in supply line if inlet pressure can exceed 14 inches w.c. at any time. Adjust lockup regulator for 14 inches w.c. maximum.

Figure 7-2Inlet Pipe with Backup Wrench

Propane Gas:

￿WARNING

Knight wall mount boilers are typically shipped ready to fire on natural gas. Check boiler rating plate to determine which fuel the boiler is set for. If set to natural gas, it may be converted to LP by installing an orifice (see page 13). In order to operate on LP gas, an orifice MUST BE installed. Failure to comply could result in severe personal injury, death, or substantial property damage.

 

 

USE BACKUP WRENCH

 

 

 

 

 

 

TO PREVENT PIPE FROM

 

 

 

 

ROTATING

 

Maximum inlet gas pressure must not

NOTICE

 

exceed the value specified. Minimum

 

 

value listed is for the purposes of input

 

adjustment.

Pipe sizing for propane gas

1.Contact gas supplier to size pipes, tanks, and 100% lockup gas pressure regulator.

Propane Supply Pressure Requirements

1.Adjust propane supply regulator provided by the gas supplier for 14 inches w.c. maximum pressure.

2.Pressure required at gas valve inlet pressure port:

Maximum 14 inches w.c. with no flow (lockup) or with boiler on.

Minimum 8 inches w.c. with gas flowing (verify during boiler startup).

￿ WARNING Ensure that the high gas pressure regulator is at least 6 - 10 feet upstream of the

appliance.

49

Image 49
Contents Models 51 Contents Please read before proceeding When servicing boilerStainless steel heat exchanger Gas connection pipe Knight Wall Mount Boiler How it worksModels 51 Knight Wall Mount Boiler Ahri Rating RatingsCloset and alcove installations Installation must comply withDetermine boiler location Before locating the boiler, check1Closet Installation Minimum Required Clearances Vent and air piping PrecautionsWall mounting location Prevent combustion air contaminationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet Prepare boilerGas conversions Mounting to a wood studded wall Mounting the boilerMounting to a concrete wall Mounting to a metal studded wallDirect venting options Sidewall Vent General ventingDirect venting options Vertical Vent Air intake/vent connections Install vent and combustion air pipingSizing Requirements for installation in CanadaLength Air inlet pipe materials MaterialsAir contamination Optional room airModel Kit Number Vent fittings Material StandardPrimer Centrotherm InnoFlue SW PolypropyleneApproved Stainless Steel Vent Manufacturers Make Model Stainless steel ventFlue Flue Intake Air Adapter TerminationSidewall direct venting If using the alternate sidewall terminationVent/air termination sidewall Determine location2AClearance to Gravity Air Inlets Prepare wall penetrations Alternate Field Supplied Option Prepare wall penetrations5AMultiple Vent Terminations must also comply with -1A Multiple vent/air terminationsSidewall termination optional concentric vent Sidewall termination installationDescription and usage Sidewall termination optional concentric vent models 8Concentric Vent Dimensional DrawingMultiventing sidewall terminations 10Concentric Vent Sidewall AttachmentVent/air termination vertical Vertical direct venting2Vertical Terminations with Multiple Boilers Prepare roof penetrationsVertical termination optional concentric vent Vertical termination installationMinimum Combustion AIR Typical Multiventing vertical terminationsConcentric Venting Arrangement Alternate vertical concentric ventingAIR Inlet Flue Exhaust Seal CAP Existing Flue Outlet Existing vent as a chaseSystem water piping methods General piping information Hydronic pipingLow water cutoff device Chilled water systemNear boiler piping components Circulator sizing Near boiler piping connectionsArmstrong Pump Size GrundfosVariable speed pump setup Smart System / Multi-temperature loop control optionVariable speed pump option UP26-96 FC/VS IFC VS Stratos 1.25 3 x3Single Boiler Single Temperature Zoned with Circulators Number of Units 5Single Boiler Multiple Temperatures Required Pipe Sizes Model 8Single Boiler Zoned with Valves Model Number of Units 10Single Boiler Non-Zoned Primary/Secondary Piping Gas connections Connecting gas supply pipingPropane Gas Natural gasCheck inlet gas supply Natural Gas Pipe Capacity ChartLength of Pipe in Straight Feet for 1/2 PSI Gas Pressure Gas valve replacementInstallation must comply with Field wiringLine voltage connections Low voltage connectionsLouver proving switch Outdoor temperature sensorFlow switch ThermostatWiring of the cascade Alarm contactsSystem supply sensor Boiler management system4Low Voltage Field Wiring Connections Condensate drain Condensate disposalStart-up Freeze protection when usedCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuits Clean/Inspect Trap AssemblyInspect/fill condensate system Inspect/check condensate lines and fittingsStart the boiler Final checks before starting the boilerIf boiler does not start correctly Check system and boiler2Operating Instructions Natural Gas Propane Set space heating operationConfiguration of the cascade Verify DHW modeSet domestic hot water DHW operation General Operating informationHow the boiler operates How the control module operatesProtection features Temperature controlBoiler temperature regulation Cascade Outdoor reset operation, if usedOperation Display Sequence of operationInstaller Access modesUser 1Control Panel Knight wall mount boiler control moduleCall for Heat Operating information Dial Function Service technician Maintenance Maintenance and annual startupOwner maintenance Maintenance Check all boiler wiring Check ignition ground wiringCheck control settings Check expansion tankCleaning boiler heat exchanger Check flame signalReview with owner Oiled bearing circulators Heat Exchanger Cleaning KitsPC Interface Diagrams2Wiring Diagram