4 Sidewall direct venting
Prepare wall penetrations
Installation & Operation Manual
Figure 4-4B Polypropylene Sidewall Termination Assembly
1.Use the factory supplied wall plate as a template to locate the vent and air intake holes and mounting holes.
Air pipe penetration:
a.Cut a hole for the air pipe. Size the air pipe hole as close as desired to the air pipe outside diameter.
Vent pipe penetration:
a.Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter:
•3½ inch hole for 2 inch vent pipe
•4½ inch hole for 3 inch vent pipe
Drill 3/16" diameter holes for inserting the plastic anchors into the wall.
2. For Polypropylene Only: Install the vent and air intake |
sidewall adapters from Table 3F on page 20 into the vent |
plate. Slide the sidewall retaining bracket down the |
SIDEWALL ADAPTER (VENT)
GALVANIZED
THIMBLE
SIDEWALL
ADAPTER
(AIR)
WALL
PLATE
SIDEWALL
RETAINING
PLATE
VENT
PLATE
VENT
CAP
IMG00085
| sidewall adapters flush to the vent plate (FIG. |
3. | For PVC/CPVC Only: Install the vent and air intake |
| piping through the wall into the vent plate openings. |
| Use RTV silicone sealant to seal the air pipe. Use the |
| cement/primer listed in Table 3D on page 19 to seal the |
| vent pipe. |
4. | Mount and secure the vent plate to the wall, using stainless |
| steel screws. |
5. | Seal all gaps between the pipes and wall. Seal around the |
| plate to the wall assuring no air gaps. |
6. | Assemble the vent cap to the vent plate (see FIG.'s |
| and |
| cap screw hole openings and securely attach the vent cap |
| to the vent plate. |
7. | Seal all wall cavities. |
8. | PVC/CPVC terminations are designed to accommodate |
| any wall thickness of standard constructions per the |
| directions found in this manual. |
9. | Stainless steel terminations are designed to penetrate |
| walls with a thickness up to 9.25 inches of standard |
| construction. |
Figure 4-4A PVC/CPVC Sidewall Termination Assembly
VENT AIR
Prepare wall penetrations (Alternate - Field Supplied Option)
1.Air pipe penetration:
a.Cut a hole for the air pipe. Size the air pipe hole as close as desired to the air pipe outside diameter.
2.Vent pipe penetration:
a.Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter:
•3½ inch hole for 2 inch vent pipe
•4½ inch hole for 3 inch vent pipe
b.Insert a galvanized metal thimble in the vent pipe hole as shown in FIG.
3.Use a sidewall termination plate as a template for correct location of hole centers.
4.Follow all local codes for isolation of vent pipe when passing through floors or walls.
5.Seal exterior openings thoroughly with exterior caulk.
Figure 4-4C Alternate Sidewall Termination Assembly w/Field Supplied Fittings
ELBOW
AIR PIPING
VENT PIPING
BIRD SCREEN
AIR PIPING
VENT PIPING
WALL PLATE
GALVANIZED
THIMBLE
24
CENTERLINE WIDTH
VENT PLATE
VENT CAP
GALVANIZED |
| ELBOW |
THIMBLE |
| |
|
| |
| SIDEWALL | BIRD SCREEN |
|
| |
| TERMINATION PLATE |
|