5 Vertical direct venting

Vent/air termination – vertical

￿WARNING Follow instructions below when determining vent location to avoid

possibility of severe personal injury, death or substantial property damage.

Determine location

Locate the vent/air terminations using the following guidelines:

Installation & Operation Manual

Figure 5-1APVC/CPVC/Polypropylene Vertical Termination of Air and Vent

ALTERNATE INTAKE LOCATIONS:

INTAKE PIPES MAY BE LOCATED

ANYWHERE WITHIN 24” OF VENT

PIPE

1.

The total length of piping for vent or air must not exceed

 

the limits given in the General Venting Section on page

 

16 of this manual.

2.

Prepare the vent termination and the air termination

 

elbow (FIG. 5-1A) by inserting bird screens. Bird screens

 

should be obtained locally.

3.

The vent must terminate at least 3 feet above the highest

 

place in which the vent penetrates the roof and at least

 

2 feet above any part of a building within 10 horizontal

 

feet.

BIRD SCREEN (TYPICAL)

COUPLING (FIELD SUPPLIED)

VENT OUTLET

12” MINIMUM ABOVE AIR INLET

VENT

6” MINIMUM ABOVE ROOF / SNOW LINE

COMBUSTION

AIR

4. The air piping must terminate in a down-turned 180°

return pipe no further than 2 feet from the center of the

Figure 5-1BStainless Steel Vertical Termination of Air and Vent

vent pipe. This placement avoids recirculation of flue

products into the combustion air stream.

5. The vent piping must terminate in an up-turned coupling

as shown in FIG. 5-1A. The top of the coupling must

be at least 1 foot above the air intake. When the vent

termination uses a rain cap as illustrated in FIG. 5-1B

maintain at least 36" (914 mm) above the air inlet. The

air inlet pipe and vent pipe can be located in any desired

position on the roof, but must always be no further than

ALTERNATE INTAKE LOCATIONS: INTAKE PIPES MAY BE LOCATED ANYWHERE WITHIN 24” (610 MM)

OF VENT PIPE

VENT

BIRD SCREEN

(TYPICAL)

 

2 feet (.6 m) apart and with the vent termination at least

 

1 foot for PVC and 3 feet for stainless steel, above the air

 

intake.

6.

Maintain the required dimensions of the finished

 

termination piping as shown in FIG. 5-1A.

7.

Do not extend exposed vent pipe outside of building

 

more than shown in this document. Condensate could

 

freeze and block vent pipe.

￿ WARNING Rooftop vent and air inlet terminations must terminate in the same pressure

zone, unless vertical vent sidewall air is set up as shown in the General Venting - Vertical Vent, Sidewall Air Section.

6" (152 MM) MINIMUM

ABOVE ROOF /

SNOW LINE

COM,BUSTION

AIR

VENT OUTLET

36” (914 MM) MINIMUM

ABOVE AIR INLET

8.Locate terminations so they are not likely to be damaged by foreign objects, such as stones or balls, or subject to buildup of leaves or sediment.

29

Image 29
Contents Models 51 Contents Please read before proceeding When servicing boilerStainless steel heat exchanger Gas connection pipe Knight Wall Mount Boiler How it worksModels 51 Knight Wall Mount Boiler Ahri Rating RatingsCloset and alcove installations Installation must comply withDetermine boiler location Before locating the boiler, check1Closet Installation Minimum Required Clearances Vent and air piping PrecautionsWall mounting location Prevent combustion air contaminationAreas likely to have contaminants When using an existing vent system to install a new boilerProducts to avoid When removing a boiler from existing common vent system Gas conversions Prepare boilerRemove boiler from wood pallet Mounting to a wood studded wall Mounting the boilerMounting to a concrete wall Mounting to a metal studded wallDirect venting options Vertical Vent General ventingDirect venting options Sidewall Vent Air intake/vent connections Install vent and combustion air pipingLength Requirements for installation in CanadaSizing Air inlet pipe materials MaterialsModel Kit Number Optional room airAir contamination Primer Material StandardVent fittings Centrotherm InnoFlue SW PolypropyleneApproved Stainless Steel Vent Manufacturers Make Model Stainless steel ventFlue Flue Intake Air Adapter TerminationSidewall direct venting If using the alternate sidewall terminationVent/air termination sidewall Determine location2AClearance to Gravity Air Inlets Prepare wall penetrations Alternate Field Supplied Option Prepare wall penetrations5AMultiple Vent Terminations must also comply with -1A Multiple vent/air terminationsDescription and usage Sidewall termination installationSidewall termination optional concentric vent Sidewall termination optional concentric vent models 8Concentric Vent Dimensional DrawingMultiventing sidewall terminations 10Concentric Vent Sidewall AttachmentVent/air termination vertical Vertical direct venting2Vertical Terminations with Multiple Boilers Prepare roof penetrationsVertical termination optional concentric vent Vertical termination installationMinimum Combustion AIR Typical Multiventing vertical terminationsConcentric Venting Arrangement Alternate vertical concentric ventingAIR Inlet Flue Exhaust Seal CAP Existing Flue Outlet Existing vent as a chaseSystem water piping methods General piping information Hydronic pipingLow water cutoff device Chilled water systemNear boiler piping components Circulator sizing Near boiler piping connectionsArmstrong Pump Size GrundfosVariable speed pump setup Smart System / Multi-temperature loop control optionVariable speed pump option UP26-96 FC/VS IFC VS Stratos 1.25 3 x3Single Boiler Single Temperature Zoned with Circulators Number of Units 5Single Boiler Multiple Temperatures Required Pipe Sizes Model 8Single Boiler Zoned with Valves Model Number of Units 10Single Boiler Non-Zoned Primary/Secondary Piping Gas connections Connecting gas supply pipingPropane Gas Natural gasLength of Pipe in Straight Feet for 1/2 PSI Natural Gas Pipe Capacity ChartCheck inlet gas supply Gas Pressure Gas valve replacementInstallation must comply with Field wiringLine voltage connections Low voltage connectionsLouver proving switch Outdoor temperature sensorFlow switch ThermostatWiring of the cascade Alarm contactsSystem supply sensor Boiler management system4Low Voltage Field Wiring Connections Condensate drain Condensate disposalStart-up Freeze protection when usedCheck/control water chemistry Fill and test water systemCheck for gas leaks Check thermostat circuits Clean/Inspect Trap AssemblyInspect/fill condensate system Inspect/check condensate lines and fittingsStart the boiler Final checks before starting the boilerIf boiler does not start correctly Check system and boiler2Operating Instructions Natural Gas Propane Set space heating operationSet domestic hot water DHW operation Verify DHW modeConfiguration of the cascade General Operating informationHow the boiler operates How the control module operatesProtection features Temperature controlBoiler temperature regulation Cascade Outdoor reset operation, if usedOperation Display Sequence of operationUser Access modesInstaller 1Control Panel Knight wall mount boiler control moduleCall for Heat Operating information Dial Function Owner maintenance Maintenance Maintenance and annual startupService technician Maintenance Check all boiler wiring Check ignition ground wiringCheck control settings Check expansion tankReview with owner Check flame signalCleaning boiler heat exchanger Oiled bearing circulators Heat Exchanger Cleaning KitsPC Interface Diagrams2Wiring Diagram