d)After the prepurge, the control module energizes the gas control valve and the spark for 4.5 seconds. If a flame is established and proved, the control allows the flame to stabilize for 5 seconds at the combustion fan ignition speed setting. If the flame fails to prove, the control module will attempt to light the burner 4 more times. If a flame is still not established, the control will lockout.

e)Once the flame stabilization period has ended, the MCBA allows the burner to modulate. The actual firing rate is dependent upon the measured current and recent differences between the set point temperature and the supply temperature. If an outdoor sensor is connected to the control module and the boiler is responding to a call for heat, the set point temperature will be determined by the outdoor reset curve shown in Figure 12.4.

f)Once the set point temperature is reached, the MCBA will turn the burner off and allow the combustion fan to operate in postpurge for 35 seconds before it turns off.

g)The central heating pump will continue to operate until the room thermostat has been satisfied.

h)A demand for domestic hot water (DHW) is given priority on FCM series boilers. If a call for DHW is received while the boiler is responding to a call for heat, the heating circulator is deenergized until the call for DHW is satisfied.

Figure 12.4: Outdoor Reset Curve

57

Image 57
Contents Freedom Table of Contents Product Description SpecificationsII Specifications Maximum Vent LengthsIV Locating the Boiler III Before InstallingClearances To Combustible Or Non-combustible Material Clearances from Vent Piping to Combustible Construction Mounting The Boiler Wall MountingFloor Mounting Wall Mounting Hole Locations Boiler Mounting/Hardware VI Air for Ventilation Page Vent System Design VII VentingPage Or PVC Summary of Horizontal Venting OptionsHorizontal Concentric Venting Vent Option Size Vent U.S. Boiler Concentric Vent Components Vent Option6c Positioning Vent Terminal Under Overhangs VENT/ AIR Intake Fitting Equivalent Length Roof Summary of Vertical Venting OptionsNever Common Vent a FCM Boiler with Other Appliances Removing an Existing Boiler From a Common ChimneyAssembly of U.S. Boiler 60/100mm Concentric Venting 11 Dimension L 12 Cutting Outer Pipe 14 Preparing Terminal Section for Installation in the Wall 16 Installation of Stainless Steel Vent Collar Assembly of Stainless Steel Venting17a Star-34 Connection to Vent Collar 18 Z-Vent III Connection to Vent Collar 19 SAF-T Vent EZ Seal Connection to Vent Collar 20 FasNSeal Connection to Vent Collar Condensate Trap and Drain Line 21 Condensate Piping Arrangement Gas Connection To Boiler Viii Gas PipingIX System Piping General System Piping PrecautionsSystem Design Flow Requirements Through BoilerMethod 1 Primary/Secondary Piping Piping Method #1 Heat Only Piping Method #1 Heat + Indirect Water Heater 4b Piping Method #1 Indirect Water Heater Loop Piping Shaded Pipe and Circulator Sizing for Indirect Water Heater Loop Pipe and Circulator Sizing for Boiler LoopFitting Equivalent Lengths Boiler Head Loss Standard Piping Installation RequirementsPiping for Special Situations 11 Chiller Piping Wiring Wiring Connections Diagram Ladder Diagram Page Never Attempt to Fill a HOT Empty Boiler XI Start-up and CheckoutWater Quality and Boiler Water Additives FCM Series Lighting and Operating Instructions SWT Typical CO2/O2 Combustion Readings Range Gas Valve DetailPage XII Operation Normal Display In Standby ModePage Basic Menu Tree First Digit Boiler Status Boiler StatusOutdoor Reset Curve XIII. Service and Maintenance Page No Error Code Displayed XIV. TroubleshootingCode Condition Possible Causes Soft Lockout Codes DisplayedHard Lockout Codes Displayed XV Parts Page KEY Description Parts ListPage Parts List Page Page Page DISP4D 150 151 152 153 154 155 156 157 158 159 160 161 162 Page Page Page Page Page Limited Warranty