Burnham 101008-01R1-2/07 manual XIV. Troubleshooting, No Error Code Displayed

Page 60

XIV. Troubleshooting

WARNING

Turn off power to boiler before replacing fuses or working on wiring.

A.Troubleshooting problems where no error code is displayed:

TABLE 14.1: NO ERROR CODE DISPLAYED

CONDITION

POSSIBLE CAUSES

Display Blank, Fan off, LWCO lights off

• No 120VAC Power at boiler. Check breaker and wiring between breaker panel

and boiler

 

 

• Loose 120VAC connection wiring between boiler J-Box and MCBA

Display Panel Blank, Fan running

• Blown “F1” fuse in MCBA (see Figure 13.2 for location). Replace with 5A fuse

 

provided

 

• Defective AT250 transformer

Display reads “U.125” continuously, Fan running

• Blown “F3” fuse in MCBA (see Figure 13.2 for location). Replace with 4A slow-

 

blow fuse provided

Boiler not responding to call for heat, Status code on

• Boiler is not seeing call for heat. Check thermostat or zone wiring for loose

display =”0” (see Figure 11.1)

connection, miswiring, or defective thermostat/zone control.

Boiler fires, but display panel is blank

• Loose ribbon cable

• Defective display

 

Figure 14.2: MBCA Fuse Location

60

Image 60
Contents Freedom Table of Contents Specifications Product DescriptionII Specifications Maximum Vent LengthsIII Before Installing IV Locating the BoilerClearances To Combustible Or Non-combustible Material Clearances from Vent Piping to Combustible Construction Mounting The Boiler Wall MountingFloor Mounting Wall Mounting Hole Locations Boiler Mounting/Hardware VI Air for Ventilation Page VII Venting Vent System DesignPage Summary of Horizontal Venting Options Or PVCHorizontal Concentric Venting Vent Option U.S. Boiler Concentric Vent Components Vent Option Size Vent6c Positioning Vent Terminal Under Overhangs VENT/ AIR Intake Fitting Equivalent Length Summary of Vertical Venting Options RoofRemoving an Existing Boiler From a Common Chimney Never Common Vent a FCM Boiler with Other AppliancesAssembly of U.S. Boiler 60/100mm Concentric Venting 11 Dimension L 12 Cutting Outer Pipe 14 Preparing Terminal Section for Installation in the Wall Assembly of Stainless Steel Venting 16 Installation of Stainless Steel Vent Collar17a Star-34 Connection to Vent Collar 18 Z-Vent III Connection to Vent Collar 19 SAF-T Vent EZ Seal Connection to Vent Collar 20 FasNSeal Connection to Vent Collar Condensate Trap and Drain Line 21 Condensate Piping Arrangement Viii Gas Piping Gas Connection To BoilerGeneral System Piping Precautions IX System PipingSystem Design Flow Requirements Through BoilerMethod 1 Primary/Secondary Piping Piping Method #1 Heat Only Piping Method #1 Heat + Indirect Water Heater 4b Piping Method #1 Indirect Water Heater Loop Piping Shaded Pipe and Circulator Sizing for Boiler Loop Pipe and Circulator Sizing for Indirect Water Heater LoopFitting Equivalent Lengths Standard Piping Installation Requirements Boiler Head LossPiping for Special Situations 11 Chiller Piping Wiring Wiring Connections Diagram Ladder Diagram Page XI Start-up and Checkout Never Attempt to Fill a HOT Empty BoilerWater Quality and Boiler Water Additives FCM Series Lighting and Operating Instructions SWT Gas Valve Detail Typical CO2/O2 Combustion Readings RangePage Normal Display In Standby Mode XII OperationPage Basic Menu Tree Boiler Status First Digit Boiler StatusOutdoor Reset Curve XIII. Service and Maintenance Page XIV. Troubleshooting No Error Code DisplayedSoft Lockout Codes Displayed Code Condition Possible CausesHard Lockout Codes Displayed XV Parts Page Parts List KEY DescriptionPage Parts List Page Page Page DISP4D 150 151 152 153 154 155 156 157 158 159 160 161 162 Page Page Page Page Page Limited Warranty