Blodgett SHO-G manual Double Section Assembly Oven Leveling

Page 11

Installation

Oven Assembly

DOUBLE SECTION ASSEMBLY

OVEN LEVELING

1.Secure the short legs to the bottom sections as described.

2.Place the upper section in position on top of the lower oven.

3.Attach the stacking brackets using the re- maining 5/16” bolts shipped with the ovens.

4.Attach the flue connector.

WARNING!!

When stacking ovens be sure to remove the single oven flue boxes prior to attach- ing three-piece connector.

After assembly, the oven should be leveled and moved to the operating location.

1.The oven can be leveled by adjusting the feet or casters located on the bottom of each leg.

Flue

Connector

Figure 7

7

Image 11
Contents SHO-G Avertissement Reputation YOU can Count on Page Table of Contents/Table des Matières Ca na d a a nd G e nera l Ex p o rt Oven Description and SpecificationsIntroduction S Speci Fications SH1G/ABOven Components Oven Location InstallationDelivery and Location Delivery and InspectionNSF Bolts Oven AssemblyLow Profile Casters for Double Stacked Ovens Caster AssemblyLEG Attachment Casters for Single and Double Stacked OvensDouble Section Assembly Oven Leveling Ventilation Canadian installationsAustralia and general export installations Installing the canopy hood draft diverterOven Single Double 15cm Installing the draft hoodDirect Flue Arrangement Flue DiameterUtility Connections --- Standards and Codes General export installationsGAS Piping Gas ConnectionManifold Pressure Natural Propane Pressure Regulation and TestingInlet Pressure Natural Propane KPaGAS Hose Restraint Electrical Connection Electrical SpecificationsInitial Startup Adjustments Associated with Initial InstallationGeneral safety tips Safety InformationSafety Tips What to do in the event of a power failureOperation Standard ControlControl Description Operating Tips General Guidelines for Operating PersonnelCheese Product Temperature Time # Shelves MeatsPoultry Fish and SeafoodPreventative Maintenance MaintenanceCleaning and Preventative Maintenance Cleaning the OvenPossible Causes Suggested Remedy Troubleshooting GuideDescription et Spécifications du Four Specifications Pour GAZ -- SH1G/ABÉléments du Four Implantation DU Four Livraison et ImplantationLivraison ET Inspection Boulons NSF Montage du FourRoulettes de bas profile pour deux fours super- posés Assemblage DES PiedsMontage DES Roulettes Roulettes pour four simple ou pour four super- posésMise À Niveau DU Four Montage DE LA Section DoubleAvertissement Hotte D’ÉVACUATION Type Voûte Installation aux États-- Unis et au CanadaGénéralités concernant les installations à l’ex- portation Installation du déviateur de tirageFour Simple Double Installation de la hotte de tirageEN Prise Directe Diamètre DU CheminéeÉquipement De Service d’alimentation De Gaz si Branchements de Service --- Normes et CodesExemple Longeur Dimensions nominales De conduit PiedsBranchement de Gaz Conduit DE GAZPression au collecteur Gaz Naturel Gaz Propane Réglage ET Test DE PressionPression à l’entrée Gaz Naturel Gaz Propane Retenue DU Tuyau DE GAZ Et Canada Raccordement ÉlectriqueSpécifications Électriques Mise en Marche Initiale Réglages À Faire Lors DE L’INSTALLA- Tion InitialeQue faire en cas de panne de secteur UtilisationInformations de Sécurité Conseils DE SécuritéUtilisation Commandes standardDescription DES Commandes Conseils Consignes Générales à l’Intention des UtilasateursFromages Aliment Température Durée Étagères ViandesVolailles Poisson et Fruits de MerEntretien Préventif EntretienNettoyage et Entretien Préventif Nettoyage DES FoursCauses Probables Suggestion Guide de Détection des PannesGuide de Détection des Pannes Insert Wiring Diagram Here Placer Schéma DE Câblage ICI