Blodgett SHO-G manual Initial Startup, Adjustments Associated with Initial Installation

Page 19

Installation

Initial Startup

The following is a check-list to be completed by qualified personnel prior to turning on the appliance for the first time.

jOpen the manual shut-off valve at the rear of the oven.

jRemove the control panel and combustion covers.

jTurn the combination valve’s manual shut-off to the on position.

jTurn the selector switch to Cook, and the ther- mostat to 500_F (260_C).

The oven main burner lights, and the Oven Ready Light comes on. With the main burner on, check the following.

jVerify there are no gas leaks, by checking all gas connections with a soapy water solution.

jVerify that the inlet pressure is correct. The in- let pressure can be checked at the pressure tap located on the combination valve’s inlet side.

jVerify that the manifold pressure is correct. The manifold pressure can be checked at the pressure tap located on the manifold.

jIf the above pressure readings are set to the recommended pressure requirements, allow the oven to burn-off for 2 hours. If the pressure readings are not set correctly, turn off the oven and readjust accordingly.

WARNING

The break in procedure burns off excess oils present in the metals during fabrica- tion. Smoke may be produced. Proper ventilation is required.

ADJUSTMENTS ASSOCIATED WITH INITIAL INSTALLATION

Each oven, and its component parts, have been thoroughly tested and inspected prior to ship- ment. However, it is often necessary to further test or adjust the oven as part of a normal and proper installation. These adjustments are the responsibility of the installer, or dealer. Since these adjustments are not considered defects in material or workmanship, they are not cov- ered by the Original Equipment Warranty. They include, but are not limited to:

Dcalibration of the thermostat D adjustment of the doors

D burner adjustments D leveling

D testing of gas pressure D tightening of fasteners.

No installation should be considered complete without proper inspection, and if necessary, adjustment by qualified installation or service personnel.

15

Image 19
Contents SHO-G Avertissement Reputation YOU can Count on Page Table of Contents/Table des Matières Ca na d a a nd G e nera l Ex p o rt Oven Description and SpecificationsIntroduction S Speci Fications SH1G/ABOven Components Oven Location InstallationDelivery and Location Delivery and InspectionNSF Bolts Oven AssemblyLow Profile Casters for Double Stacked Ovens Caster AssemblyLEG Attachment Casters for Single and Double Stacked OvensDouble Section Assembly Oven Leveling Ventilation Canadian installationsAustralia and general export installations Installing the canopy hood draft diverterOven Single Double 15cm Installing the draft hoodDirect Flue Arrangement Flue DiameterUtility Connections --- Standards and Codes General export installationsGAS Piping Gas ConnectionManifold Pressure Natural Propane Pressure Regulation and TestingInlet Pressure Natural Propane KPaGAS Hose Restraint Electrical Connection Electrical SpecificationsInitial Startup Adjustments Associated with Initial InstallationGeneral safety tips Safety InformationSafety Tips What to do in the event of a power failureControl Description Standard ControlOperation Operating Tips General Guidelines for Operating PersonnelCheese Product Temperature Time # Shelves MeatsPoultry Fish and SeafoodPreventative Maintenance MaintenanceCleaning and Preventative Maintenance Cleaning the OvenPossible Causes Suggested Remedy Troubleshooting GuideDescription et Spécifications du Four Specifications Pour GAZ -- SH1G/ABÉléments du Four Livraison ET Inspection Livraison et ImplantationImplantation DU Four Boulons NSF Montage du FourRoulettes de bas profile pour deux fours super- posés Assemblage DES PiedsMontage DES Roulettes Roulettes pour four simple ou pour four super- posésAvertissement Montage DE LA Section DoubleMise À Niveau DU Four Hotte D’ÉVACUATION Type Voûte Installation aux États-- Unis et au CanadaGénéralités concernant les installations à l’ex- portation Installation du déviateur de tirageFour Simple Double Installation de la hotte de tirageEN Prise Directe Diamètre DU CheminéeÉquipement De Service d’alimentation De Gaz si Branchements de Service --- Normes et CodesExemple Longeur Dimensions nominales De conduit PiedsBranchement de Gaz Conduit DE GAZPression à l’entrée Gaz Naturel Gaz Propane Réglage ET Test DE PressionPression au collecteur Gaz Naturel Gaz Propane Retenue DU Tuyau DE GAZ Spécifications Électriques Raccordement ÉlectriqueEt Canada Mise en Marche Initiale Réglages À Faire Lors DE L’INSTALLA- Tion InitialeQue faire en cas de panne de secteur UtilisationInformations de Sécurité Conseils DE SécuritéDescription DES Commandes Commandes standardUtilisation Conseils Consignes Générales à l’Intention des UtilasateursFromages Aliment Température Durée Étagères ViandesVolailles Poisson et Fruits de MerEntretien Préventif EntretienNettoyage et Entretien Préventif Nettoyage DES FoursCauses Probables Suggestion Guide de Détection des PannesGuide de Détection des Pannes Insert Wiring Diagram Here Placer Schéma DE Câblage ICI