Customizing and Updating the PDU

4.At the front of the PDU, connect the power cord’s individual wires:

a.If you have branch current monitoring installed, route the phase conductor through a current sensor. If it is a three-phase cable, route the L1, L2, and L3 wires through a current sensor.

b.Connect the L1, L2, and L3 wires to the circuit breaker(s). The illustration below shows single pole circuit breakers; however, you can also connect three-pole breakers.

c.Connect the neutral wire to the closest open termination point on the Neutral Bar (N).

d.Connect the ground wire to the closest open termination point on the Ground Bar (G).

N

G

80kW InfraStruXure PDU—Operation and Configuration