Warnings

Installation/Maintenance

Only a certified electrician can perform these tasks:

Connect the InfraStruXure PDU to utility power

Connect the cross tie output breaker to another InfraStruXure PDU

Connect a switch to the EPO interface on the InfraStruXure PDU

Only a certified electrician or an APC Field Service Engineer can perform these tasks:

Connect the PDU to the Symmetra PX UPS

Perform maintenance of the PDU

When you connect the PDU to utility power, you must install a circuit breaker to protect the PDU against over-current. Determine the type of circuit breaker that you need to install:

Input Voltage

Circuit Breaker Size

208V350A

480V150A

600V125A

Maintenance performed while the PDU is receiving input power

APC does not recommend that you perform maintenance of the PDU while it is receiving input power. However, due to the critical nature of data center loads, this may occur. If you must perform maintenance while the PDU is receiving input power, observe the following precautions to reduce the risk of electric shock:

1.Never work alone.

2.Perform the maintenance only if you are a certified electrician who is trained in the hazards of live electrical installation.

3.Know the procedure for disconnecting electricity to the PDU and the data center in case of an emergency.

4.Wear appropriate personal protective equipment.

5.Use double-insulated tools.

6.Always follow local and site regulations when working on the PDU.

2

80kW InfraStruXure PDU—Operation and Configuration

Page 10
Image 10
American Power Conversion PD80KF6FK1-M, PD80KG6FK1-M, PD80KL6FK1-M manual Installation/Maintenance