114 en | LTC 8600 LTC 8800 Series |
Appendix B Installation Checklists
A simplified guide for those who are already familiar with installing and program- ming Allegiant systems.
MAIN BAY HARDWARE INSTALLATION
Unpack equipment and verify that items have been received without carrier damage.
Install power supply (do not turn ON) and CPU module.
If applicable, install bay into EIA
Install video input module(s) following proper termination procedures. Install video output module(s).
Connect camera inputs and monitor outputs to appropriate connections on equip- ment bay(s).
Connect system keyboards, any alarm interface unit(s), and any signal distribution unit to main bay.
Set CPU DIP switches to activate desired features.
Apply main AC power to equipment.
Verify system is operating properly then begin appropriate programming.
PROGRAMMING VIA SYSTEM KEYBOARD
Enter system time (User Function 7) and date (User Function 8). Enter Camera ID titles (User Function 9), and if desired, adjust monitor overlay displays (User Function 4, 5, & 6 or 24, 25 & 26).
Enter desired Sequences.
Configure and test alarm response mode.
SATELLITE CONFIGURATION HARDWARE INSTALLATION
Main Site:
Install main Allegiant bay and appropriate accessory products accordingly. Verify biphase control code line is run to each satellite site.
Attach trunk line inputs, local camera inputs, and monitor outputs to main Allegiant bay. Apply main AC power to equipment.
Program Camera ID table using LTC 8059 Master Control Software package.
Switch all unused monitor outputs located at main site to display a 'local' camera input.
Satellite Site(s):
Install satellite switcher and appropriate accessory products accordingly.
Connect biphase code line to LTC 8780 Data Converter unit and configure according to desired satellite address and switcher's baud rate.
If necessary, program satellite switcher for desired camera titles and any other related requirements.