3. INSTALLATION
(1)
(2) Conversion harness
Connect the connector for the
* Be sure to make the ground connection. (Refer to
When the work clamp switch (left) is depressed, both work clamps are lowered, and when the start switch (right) is depressed, the sewing machine starts sewing.
* The work clamp lowering method can be changed using memory switch No. 002. (Refer to
3042B
Work clamp switch
Start switch
4923Q
1. Gently tilt back the machine head.
2. Pass the cord bundle through the hole in the work table.
3. Loosen the two screws (1), and then open the cord presser plate (2) in the direction of the white arrow and pass the cord bundle through the opening.
4. Securely connect the connectors as indicated in the table below.
(Refer to following page.)
NOTE:
• Check that the connector is facing the correct way, and then insert it firmly until it locks into place.
• Secure the cables with cable ties and cord clamps, while being careful not to pull on the connector.
3233B
(Continued on next page.)