Carrier 48AK, 48EW, 48AW, 48EK Start-Upchecklist, Pre-Start-Up, Electrical, Temperatures, Pressures

Models: 48EJ 48AJ 48AK 48EK 48AY020-060 48AW 48EY024-068 48EW

1 118
Download 118 pages 46.64 Kb
Page 117
Image 117

START-UP CHECKLIST

MODEL NO.: _________________________________

SERIAL NO.: ______________________________________

SOFTWARE VERSION (SEE FIG. 27): ____________

TECHNICIAN: ____________________________________

DATE: _______________________________________

 

PRE-START-UP:

…VERIFY THAT DIP SWITCH SETTINGS ARE CORRECT

…VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT

…REMOVE ALL COMPRESSOR SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTRUCTIONS

…VERIFY INSTALLATION OF ECONOMIZER HOOD

…VERIFY INSTALLATION OF ALL OPTIONS AND ACCESSORIES

…VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT

…CHECK GAS PIPING FOR LEAKS

…CHECK THAT RETURN-AIR FILTER AND OUTDOOR-AIR FILTERS ARE CLEAN AND IN PLACE

…VERIFY THAT UNIT IS LEVEL WITHIN TOLERANCES FOR PROPER CONDENSER DRAINAGE

…CHECK FAN WHEELS AND PROPELLERS FOR LOCATION IN HOUSING/ORIFICE, AND SETSCREW IS TIGHT

…VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED

…VERIFY THAT SUCTION, DISCHARGE, AND LIQUID SERVICE VALVES ON EACH CIRCUIT ARE OPEN

…VERIFY THAT CRANKCASE HEATERS HAVE BEEN ON 24 HOURS BEFORE START-UP.

START-UP:

ELECTRICAL

SUPPLY VOLTAGE

L1-L2

__________ L2-L3 __________ L3-L1 __________

 

COMPRESSOR AMPS — COMPRESSOR NO. 1

L1

__________

L2

__________

L2 _________

COMPRESSOR AMPS — COMPRESSOR NO. 2

L1

__________

L2

__________

L2 _________

SUPPLY FANS AMPS

(CV)

________

 

EXHAUST FAN AMPS

__________

 

 

(VAV)

________ *

 

 

 

 

 

*VAV fan supply amps reading must be taken with a true RMS meter for accurate readings.

 

TEMPERATURES

 

 

 

 

 

 

 

OUTDOOR-AIR TEMPERATURE

__________ F DB (Dry Bulb)

 

 

 

RETURN-AIR TEMPERATURE

__________ F DB__________

F WB (Wet Bulb)

 

COOLING SUPPLY AIR

 

__________ F

 

 

 

 

GAS HEAT SUPPLY AIR

 

__________ F

 

 

 

 

PRESSURES

 

GAS INLET PRESSURE

__________ IN. WG

GAS MANIFOLD PRESSURE

STAGE NO. 1 __________ IN. WG

REFRIGERANT SUCTION

CIRCUIT NO. 1 __________ PSIG

REFRIGERANT DISCHARGE

CIRCUIT NO. 2 __________ PSIG

STAGE NO. 2 __________ IN. WG

CIRCUIT NO. 2__________ PSIG

CIRCUIT NO. 2__________ PSIG

…VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS ON PAGES 93 AND 94.

CL-1

Page 117
Image 117
Carrier 48AK, 48EW, 48EY024-068, 48AW, 48AY020-060, 48EK Start-Upchecklist, Pre-Start-Up, Electrical, Temperatures, Pressures