Chapter 3 Installing the Switch
Attaching the Interface Cables
Step 9 Do not turn source DC power on at this time. Continue the installation process by attaching the interface cables to the chassis ports.
Figure 3-6 Connecting Source DC to the DC-Input Power Supply (PWR-C49-300DC)
+ -
PWR - |
|
60VAC | |
8A | |
INPUT | OUTPUT |
OK | |
| OK |
+ |
|
|
| PWR - |
|
- | ||
|
| |
| 60VAC | |
| 8A | |
| INPUT | OUTPUT |
| OK | |
|
| OK |
1
207517
1
Attach the source DC leads to the power supply terminal block in the following order:
•Ground
•
•(+) positive
Attaching the Interface Cables
This section covers attaching the interface cables to the chassis front panel connectors. The section is divided into the following topics:
Connecting to the Downlink Ports, page
Installing Uplink Port Transceivers and Cables, page
Connecting to the Ethernet Management Port, page
Connecting to the Console Port, page
|