2.4Preliminary Checks

Before you install the UPS hardware you should carry out the following preliminary checks:

1.Verify that the UPS room satisfies the environmental conditions stipulated in the equipment specification, paying particular attention to the ambient temperature and air exchange system.

2.Remove any packaging debris, then visually examine the UPS and battery equipment for transit damage, both internally and externally. Report any such damage to the shipper immediately.

2.5Installation Drawings

The following diagrams illustrate the key mechanical characteristics of the various UPS system cabinets

Fig 2-1: Overall General Arrangement for 130 kVA Single Phase 110V UPS with 6 Pulse rectifier Single Module and ‘1+N’

Fig 2-2: Cable entry and Foundation details for 130 kVA Single Phase 110V UPS with 6 Pulse rectifier Single Module and ‘1+N’.