3-2Installing Server

Installation

This section describes installation of NEC Express5800/ft series.

Tower Model

IMPORTANT: NEC Express5800/ft series is a precision instrument. You should ask maintenance personnel to install it.

Select a suitable site for tower model.

CAUTION

Observe the following precautions to use the equipment safely. There are risks of a burn, injury, or damage to physical assets. For details, see “Notes for Safe Handling” in Chapter 1.

Remove all modules before moving the equipment.

Do not install the equipment in non-designated places.

Close enough to connect the mouse and the display.

Floor or a level and robust desk or table

Clean and tidy room

Location with an open space of 1m or more on the front side, 50 cm or more on the rear side, and 15cm or more on the right and left sides of the server. (The front bezel extrudes about 50 mm from the right side of the server when fully opened.)

Room that can maintain the following conditions: [When operating]

Temperature: 10 to 35ºC*

Humidity: 20 to 80%

Temperature gradient: ±10ºC/hr

Atmospheric pressure: 749 to 1040hpa [When not operating] Temperature: 5 to 40ºC*

Humidity: 10 to 80%

Temperature gradient: ±15ºC/hr

Atmospheric pressure: 749 to 1040hpa

100V - 120 V or 200V - 240 V parallel bi-polar power outlet with grounding

Wall outlet within the reach of supplied power cord.

UPS to prevent momentary voltage drop due to power failure or lightning *

*Optional. UPS is recommended for best use of features of NEC Express5800/ft series.

*It is recommendable to use the server in a room where temperature can be kept between 15 and 25ºC.