To unpack and position the MGC-50:

1.When you receive your MGC-50, inspect the equipment for damage and verify that the components match the packing slip. If you did not receive a component or if there is damage to the system, notify Polycom immediately.

Wood Packing Case

Carrying Strap

Lock in Closed Position

Lock in Open Position

Figure 2-11: MGC-50 package

2.Place the MGC-50 unit on a stable flat surface in a location that meets the MGC-50’s environment requirements, which are:

Operating temperature: 10°–40°C (50°–104°F)

Humidity: 15%–90% noncondensing

Altitude: Up to 3,000m (10,000ft)

ESD: +8 kV

2-21