6)Install the Container Stacker 1 to the Container Stacker 2. The screw is the thing of the temporary stopping.

Container stacker 1

M4x12 screws

M4x12 screws

Container stacker 2

M4x12 screws

Frame projection part

7)In order to adjust the height of Container stacker, turn 180 degrees each of four leveling bolts, and satisfy the following conditions, and bolt the screw of a temporary tight.

(1)When Front cover R is shut and it looks into the space between Container stacker 2 and Container stacker 1 from a front side, the height of the Frame’s projection of

Container stacker and the Guide plate U’s projection is the same. [Note] As for the way of opening front cover L, refer to the item 3.3.

Stacker frame

Guide plate U

Level Meter

Projection

Projection

Front cover R

Same height

Connection part details

Leveling bolt

Front cover L

 

 

II

L

01

 

 

Preparation for Installation 4-33

Page 81
Image 81
Ricoh 70E installation manual Container stacker M4x12 screws