Xantrex Technology PV100S-480 installation manual Operational Safety Procedures, Lockout and Tag

Models: PV100S-480

1 90
Download 90 pages 29.08 Kb
Page 12
Image 12
Operational Safety Procedures

Safety

Operational Safety Procedures

Never work alone when servicing this equipment. A team of two is required until the equipment is properly de-energized, locked-out and tagged, and verified de- energized with a meter.

Thoroughly inspect the equipment prior to energizing. Verify that no tools or equipment have inadvertently been left behind.

Lockout and Tag

Safety requirements mandate that this equipment not be serviced while energized. Power sources for the PV100S must be locked-out and tagged prior to servicing.

A padlock and tag should be installed on each energy source prior to servicing.

WARNING: Shock Hazard

Review the system schematic for the installation to verify that all available energy sources are de-energized. DC bus voltage may also be present. Be sure to wait the full 5 minutes to allow the capacitors to discharge completely.

The PV100S can be energized from both the AC source and the DC source. To ensure that the inverter is de-energized prior to servicing, lockout and tag the PV100S using the following procedure.

1.Open, lockout, and tag the incoming power at the utility main circuit breaker.

2.Open, lockout, and tag the AC Disconnect Switch (S1) on the AC Interface Enclosure. See Figure 1-4 on page 1–9 for the location of the AC Disconnect Switch.

3.Open, lockout, and tag the DC Disconnect Switch (S2) on the DC Interface Enclosure. See Figure 1-4 on page 1–9 for the location of the DC Disconnect Switch.

4.Using a confirmed, accurate meter, verify all power to the inverter is de- energized. A confirmed, accurate meter must be verified on a known voltage before use. Ensure that all incoming energy sources are de-energized by checking the following locations.

a)Inverter Terminals: TB4-A, TB4-B, TB4-C (Phase A, B, C) See Figure 3-15 on page 3–16.

b)Utility Terminals: Bottom of S1-2T1, S1-4T2, S1-6T3 See Figure 3-16 on page 3–16.

c)PV Terminals: Bottom of TB3-1, TB3-2, TB3-3 (PV+, PV-, GND) See Figure 3-19 on page 3–19.

x

152315 Rev C

Page 12
Image 12
Xantrex Technology PV100S-480 installation manual Operational Safety Procedures, Lockout and Tag, WARNING Shock Hazard