Hipulse - Single Phase ‘1+N’ UPS System | 130 kVA - 110V |
2.4Preliminary Checks
Before you install the UPS hardware you should carry out the following preliminary checks:
1.Verify that the UPS room satisfies the environmental conditions stipulated in the equipment specification, paying particular attention to the ambient temperature and air exchange system.
2.Remove any packaging debris, then visually examine the UPS and battery equipment for transit damage, both internally and externally. Report any such damage to the shipper immediately.
2.5Installation Drawings
The following diagrams illustrate the key mechanical characteristics of the various UPS system cabinets