5.11 Setting the Battery Test
A
For the following test to be ‘meaningful’ as part of the UPS commissioning procedure, the batteries should be fully charges prior to the test being carried out. The UPS rectifier section must be therefore allowed to be operated with the battery connected for several hours to provide the battery with an adequate initial charge.
CAUTION
Do not continue with this procedure if the battery is not yet charged.
1.From the default window press the ENTER key: the Main Menu window will display.
2.Select FUNCTION and press ENTER key.
3.When the password has been completed press the ENTER key.
4.Select the BATTERY TEST and press ENTER key.
5.Verify that the parameters entered in the battery test set up menu are appropriate. If not then enter the correct set up parameters (FUNCTION à BATTERY TEST à SET UP)
6.Press ESC key to return to the battery test menu screen.
7.Using the ‘UP’ menu button, select ‘YES’ (Y), then press enter to initiate an immediate battery test.
8.Step back to default screen, by continuously pressing the ESC button and verify that the message: BATTERY UNDER TEST is displayed. The green LED battery bargraph will indicate the remaining battery time.
Note: If the UPS is allowed to run in this condition the battery bargraph LED’s will progressively turn off the indicating the remaining autonomy time.
9.The battery will be tested for the selected ‘DURATION’ time after which the UPS will revert to normal operation.
Note: If the battery fails the test, the rectifier will immediately return to the float mode and the
‘BATTERY: TEST FAILED’ alarm will be displayed on the default screen.