Chapter 3 - Unpacking and Installing Frame

Remove Packing Materials

Note: Temporarily store all packaging materials in case any of the system components must be returned to APC.

1.Remove the Shipping Bands - Using appropriate precau- tions, cut the plastic shipping bands.

2.Remove the Cardboard - Using care not to damage the surface of the Power Array, remove the cardboard from the frame. Save the electrical installation instructions that are printed on the packaging material.

3.The Pallet Ramp - The pallet ramp is shipped under the cardboard cap on top of the frame. Cautiously remove the ramp from the top of the frame.

4.Remove the Cover Grills - Remove the grill covers from the frame. Grasp a grill cover by the side finger hold, and pull straight forward. Set the covers to one side. Do not scratch them.

5.Leveling Feet - Fully retract each of the four leveling feet located near the casters on the bottom of the frame.

Frame

Restraint

Ramp

Holes

Fig 3-2 Frame Restraint and Ramp Holes

Remove the Frame from the Pallet

1.Loosen Rear Bracket Screws - Loosen the two phillips- head screws securing the brackets at the rear of the frame.

2.Remove Two Frame Restraint Screws - See Figure 3-2. Remove the frame restraint screws. Use the cloth handle to remove the frame restraint from the pallet. Place the frame restraint and two screws aside.

3.Install the Ramp - Position the ramp so that the installation bolts line up with the ramp bolt holes on the pallet. Install the ramp onto the pallet as shown in Figure 3-3.

Fig 3-3 Frame Pallet Ramp

4.Roll the Frame from the Pallet - The following operation requires two people. Holding the frame near the center, care- fully roll it down the ramp and onto the floor. (The frame is equipped with casters.)

5.Roll the Frame to the Installation Site - Carefully roll the frame from the staging area to the final installation site.

6.Shipping Material Storage - Gather and store all shipping materials.

Moving Battery & Power Modules

1.Move Battery and Power Modules On Pallet - Use the pallet jack to move the modules pallet(s) to the installation site. Remove the outer packaging materials.

2.Stack Modules - Carefully stack the boxed battery and power modules near the installation site. Leave adequate space for the electrican to install wiring to the frame.

3-2

Image 27
Contents Page 0660 Main Tech Support+353 91 Toll-Free NumbersRadio Frequency Interference Important Safety InstructionsLife Support Policy Limited WarrantyTable of Contents Index MiniFrame MasterFrame IntroductionTheory of Operation Power Processing Battery SourceFig I-2 Functional Diagram of a SymmetraTM Thank You SymmetraTM OverviewPower Processing System Battery SourceControl/User Interface Load-Disconnect Mode On-Line Operating ModeModes of Operation Bypass Operating Mode On-Battery Operating ModeImportant Information DefinitionsPage Important Safety Information Safety InformationSafety Earth Ground Indicates the pri- mary safety ground Symbols Used In This ManualSafety-2 Physical Representation Bays Power Array FrameFive Four Power Battery ModulePower Module Powerview User InterfacePower Module Battery ModuleInput Circuit Breaker Maintenance Bypass SwitchMain Intelligence Module MIM Redundant Intelligence Module RIMRear View of a Power Array Site Preparation BTU Output Space and Weight ConsiderationsTransporting Power Array to Installation Site Operating ConditionsSite Preparation Unpacking and Installing Frame Check For Damage Dimensions WeightInitial Inspection Move the FrameMoving Battery & Power Modules Remove Packing MaterialsRemove the Frame from the Pallet Wiring Requirements & Procedures Repo Switch Wiring SymmetraTM WiringInput Wiring Output WiringInput Wiring Input Wiring SpecificationsInput Wiring Procedures Ground Wiring and Input Wiring Terminal Blocks Ground Wiring Terminal BlockOutput Wiring Installation Output WiringCable Specifications Remote Emergency Power Off SwitchRepo Specifications Repo Switch InstallationVdc Repo Switch Connection Electrical Wiring TestElectrical Wiring Test/Checklist Contact Closure Repo Switch Connection11 Startup Screen Record the PowerView reportedSetting Up The Power Array Positions Setup of Power ArrayFrame Leveling Procedure Removing Grill CoversBattery Module Location of Battery Module Bays Installing the Battery ModulesProcedure for Battery Module Installation Clear all battery module bays of any debrisProcedure for Power Module Installation Installing the Power Modules10 Location of the MIM and RIM Installing the Main Intelligence Module MIMInstalling the Redundant Intelligence Module RIM Main Intelligence ModuleRemove the grill cover from the top level of the frame Installing the PowerView InterfaceRemote Placement of the PowerView Wall Mounting the PowerViewSmartSlotTM Interface Accessories Installation Test/Checklist Installation TestPower Reported SymmetraTM Power Module/Frame Capacities21 Miscellaneous Status Screen 22 Power The Load Sequence 25 Return to On-Line Mode System Setup PowerView Display Physical Features of the Powerview PowerView FunctionsPowerView Interface Navigation Keys PowerView LED IndicatorsSymbol Name Function of Key On Key EscStatus Startup ScreenTop-Level Menu Screen ControlLogging SetupAccessories DiagnosticsConfiguring & Operating the SymmetraTM Introduction Powering the Power ArrayLoad With No Redundancy Status Screen Powering the LoadsReview Status Conditions Voltage Status ScreenLoad With Redundancy Status Screen Battery Status Screen Power Status ScreenFrequency Status Screen Miscellaneous Status Screen Alarm Threshold Status Screen11 Sample Alarm Threshold Status Screen Perform a Self TestShutdown Parameter Selection Screen Configure AlarmsAlarm Thresholds Selection Screen Switching Audible Alarm Beeper OffEvent Log Screen Review Diagnostic InformationDiagnostics Menu Screen Review Logging MenuModule Replacement Module Replacement Module Failure Alarm IndicatorsReturning Modules to APC Battery Module Replacement Installing the Replacement ModuleReplacement Battery Module Verification Power Module Replacement Replacement Module VerificationRefer to for the power module installation proce- dure Installing the Replacement Redundant Intelligence Module Redundant Intelligence Module ReplacementInstalling the Replacement Main Intelligence Module Replacement MIM VerificationPowerView Interface Messages PowerView Meaning Corrective Action Message Start-Up MIM detects the RIM beforeRIM is awake Has been corrected either because PowerView Meaning Corrective Action Message# of batteries decreased Load is No Longer aboveRedundancy-select Setup-Alarms-RedundancyThreshold. Startup-Setup-Alarms Select zeroBecause of a power failure, wait for Battery modules are beingSupport. See inside front cover PowerView Display Messages Index Configuring PowerView Threshold status Electro-static discharge, 2-1 Emergency power offDescription Frame, 2-1 Modules ConfiguringDescription, 1-4 Installation Ordering information Checklist Input Output Overview RepoReplacement Modules & Accessories English Text