Page 12

2. Attach Mounting Brackets

Attach field-supplied, corrosion resistant, mounting brackets to the CVA using corrosion resistant sheet metal screws.

3. Install Exhaust Pipe

Slide the exhaust pipe through the CVA. Provide enough exhaust piping to pass through the roof and provide the minimum clearance of 12 inches between the exhaust pipe termination and the combustion air intake. With all required clearances satisfied, attach the exhaust pipe to the CVA.

INTAKE END

Exhaust Connection

Exhaust Connection

(Model IGX)

(Model IG)

DISCHARGE

END

7.Install Combustion Air Inlet Guard and Exhaust Vent Terminal

Slide the combustion air terminal over the vent pipe and fasten it to the combustion air pipe. Attach the exhaust vent terminal to the discharge end of the exhaust piping.

8. Seal Opening

Seal the opening between the roof line and the air intake pipe using an appropriate method.

Combustion Air Connection

Combustion Air Connection

(Model IGX)

(Model IG)

4. Install Combustion Air Pipe

Attach a field-supplied combustion air pipe to the concentric side of the CVA.

Be sure to provide enough combustion air piping to pass through the roof and provide the minimum clearance of 12 inches between the combustion air intake and the exterior surface of the roof. This clearance may need to be increased to allow for snow accumulation.

Be sure to maintain the minimum clearance of

12 inches between the exhaust pipe termination and the combustion air intake.

5. Install CVA Assembly

Place the CVA assembly through the roof and verify that all minimum clearance requirements as specified in these instructions are met. Secure the CVA assembly to the ceiling with corrosion resistant sheet metal screws through the mounting brackets.

6. Attach CVA Assembly to Unit

Attach the exhaust pipe to the unit’s combustion exhaust. Using an additional combustion air pipe, connect the unit’s combustion air supply intake to the combustion air connection on the CVA.

Be sure to include the required tee’s with drip legs and clean-outs.

12 Model IG / IGX Make-Up Air

®

Image 12
Contents Installation, Operation and Maintenance Manual General Safety InformationInspection and Maintenance during Storage ReceivingHandling StorageTable of Contents Clearance to Combustibles / Service ClearancesInstallation of Indoor Unit Installation of Arrangement DB / HZInstallation of Roof Mounted Unit Arrangement DBC Install Combination Curb AdaptorInstall Curb/Equipment Supports Assemble and Attach WeatherhoodInstall Exhaust Fan Install Exhaust OptionsInstall Supply Unit Installation of Evaporative Cooling Module optional Installation of Venting for Outdoor UnitsInstallation of Venting for Indoor Units Venting MethodsStandard Indoor Venting Separated Combustion Concentric VentingInstallation of Standard Indoor Venting Installing Exhaust Vent PipeVent Pipe Diameter Installation of Concentric Venting General Concentric Venting HorizontalConcentric Venting Vertical Intake END Installation of Two Pipe Venting Horizontal Seal Wall OpeningsInstallation of Two Pipe Venting Vertical Seal Roof PenetrationInstallation Electrical Wiring Wire the Evaporative Cooler optional Install Economizer Sensors optionalInstall Discharge Air Sensor optional Install DDC Interface OptionalInstallation of Gas Piping Install Additional Regulator if RequiredDetermine the Supply Gas Requirements Connect the Supply Gas LineInstallation Evaporative Cooler Piping optional Install the Water Supply LineInstall the Drain Line Check/Adjust Water LevelInstallation of Water WizardTM optional Install Normally Closed Supply Line/ SolenoidInstall Normally Open Drain Line/ Solenoid Water Wizard Valves When provided by manufacturerInstallation of Water Wizard Installation Direct Expansion DX Coil Piping optionalWire the Solenoids Wire the Temperature SensorInstall Suction Line Mount the Remote Sensing Bulb By OthersCheck Coil Piping for Leaks Evacuate and Charge the CoilInstallation of Chilled Water Coil Piping optional Installation of Building Pressure Control optionalStart-Up Blower Set-up Optional Components Reset the Temperature Setting Start-Up Furnaces all unitsStart-Up Single Stage Control Send Unit to High FireStart-Up 21 Staged Control Start-Up 81 Staged ControlSend Unit to Low Fire Check the Low Fire Manifold PressureAccess the Setpoints Menu Access the Discharge Air Temperature SettingEdit the Setting Access the Inlet Air Sensor SettingAccess the Room Override Setting High Fire Adjustment Start-Up 21 Electronic ModulationExit High Fire Mode Start-Up 41 Electronic ModulationCheck the Low Fire Manifold Pressures Access the Setpoints Menu Verify Sensor Installation Start-Up Economizer optionalSet Minimum Outside Air Set the Enthalpy Changeover Set Point optionalStart-Up Evaporative Cooling optional Start-Up Water Wizard optional Operation - Water Wizard optional External Signal a variable Check Operation VAV Units optionalBuilding Pressure Control Check Operation Recirculating Units optional Recirculation OperationBuilding Pressure Control a Damper actuator may take a fewSequence of Operation Staged Sequence Exhaust Fan Contact S1 Manually Closed optionalSequence of Operation 21 Modulation Sequence Discharge Air Temperature dtS Outside Air Temperature OAtSequence of Operation Modulation Sequence Operation Modulation Staged ControllerSequence of Operation 41 Electronic Modulation Program Revision NumberOptional Room Override ROt Light Off BlinkingSequence of Operation Electronic Modulation Sequence of Operation Staged Control Staging Control Sequence of OperationOperation and Errors Ignition Controller Following are the green LED codes of operationOption EC-1 Outside Air Temperature Reference Option EC-3 Differential Temperature ControlOperation Economizer Option EC-2 Outside Air Enthalpy ReferenceTroubleshooting Blower Does Not OperateMotor Over Amps Insufficient Airflow Too Much AirflowExcessive Noise or Vibration Single or 21 Stage Furnace Will Not Light Improper manifold pressureModulating Furnace Will Not Light Heat transformer TR2 fault Ignition controllers IC# failed Staged Furnace Will Not Light Internal high limit tripped temperature above set point Evaporative Cooler does not Operate Recirculating pump Water Blows through Evaporative CoolerAdjust the Manual Supply Valve Adjust the On Time FactorWater Wizard Improper Water Supply Maintenance Routine Belt DrivesSnow Accumulation WheelsMotors FiltersChilled Water Coils Evaporative CoolersMaintenance Fall Flushing Coils Reference Model IG Venting Connection Location Reference Model IGX Venting Connection LocationReference Model IG Single or 2 Stage Reference Model IG Staged Reference Model IG Modulation Modulating Reference Model IGX Blower Control Center Manifold Gas Pressure Test Port Staged Inch Gas Supply Manifold Gas Pressure Test Port Modulating Staged Reference Performance Table Performance TableReference Start-Up Checklist Start-Up ChecklistMaintenance Log Warranty