Greenheck Fan 470656 manual Troubleshooting, Blower Does Not Operate

Page 46

Troubleshooting

Blower Does Not Operate

Proper supply power at

No

 

 

main disconnect

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

 

 

 

24 VAC between

No

 

terminals R and X?

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

24 VAC between

No

 

terminals G and X?

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

24 VAC across

No

 

terminals 3 and X?

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

24 VAC across

No

 

terminals 4 and X?

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

24 VAC across A2 and A1 on

No

 

supply contactor (ST1)

 

 

 

 

 

 

 

Yes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Check Main Voltage

(See Blower Start-Up Step #1)

Main Disconnect (DS1) Off

(Turn Main Disconnect DS1 On)

Primary Fuses Blown

(Replace Fuses)

Main Transformer (TR1) Defective

(Replace Transformer)

Supply Switch (S2) Off

(Turn Supply Switch (S2) On)

Fire system contact (FSC) tripped/not installed

(Correct/Replace)

Supply Fan Overload (ST1 OL) Tripped

(Reset and check motor amps, reference Blower Start-Up #4)

Optional Exhaust Fan Interlocks (ST2-ST5) Open

(Correct/Replace)

(Optional) Freeze Protection (RT4) Tripped

(Reset)

(Optional) Damper Limit Switch (DL1) Holding (Wait for actuator to open fully or adjust limit switch)

(Optional) Damper Limit Switch Jumper Missing

(Install jumper, reference the unit ladder diagram for terminals)

Fan Relay (RF) is not energized

(Check for loose connection) (Repair or replace relay)

Broken Fan Belt

(Replace - Reference V-Belt drives in the Maintenance section)

Defective motor or capacitor

(Repair/Replace)

Blown Motor Fuse

(Replace)

One or more legs of 3 phase is out

(Restore missing legs)

At this time the supply contactor (ST1) should pull in,

passing power to the supply motor and the blower should start.

46 Model IG / IGX Make-Up Air

®

Image 46
Contents Installation, Operation and Maintenance Manual General Safety InformationHandling Inspection and Maintenance during StorageReceiving StorageTable of Contents Clearance to Combustibles / Service ClearancesInstallation of Indoor Unit Installation of Arrangement DB / HZInstall Curb/Equipment Supports Installation of Roof Mounted Unit Arrangement DBCInstall Combination Curb Adaptor Assemble and Attach WeatherhoodInstall Exhaust Options Install Exhaust FanInstall Supply Unit Installation of Evaporative Cooling Module optional Installation of Venting for Outdoor UnitsStandard Indoor Venting Installation of Venting for Indoor UnitsVenting Methods Separated Combustion Concentric VentingInstalling Exhaust Vent Pipe Installation of Standard Indoor VentingVent Pipe Diameter Installation of Concentric Venting General Concentric Venting HorizontalConcentric Venting Vertical Intake END Installation of Two Pipe Venting Horizontal Seal Wall OpeningsInstallation of Two Pipe Venting Vertical Seal Roof PenetrationInstallation Electrical Wiring Install Discharge Air Sensor optional Wire the Evaporative Cooler optionalInstall Economizer Sensors optional Install DDC Interface OptionalDetermine the Supply Gas Requirements Installation of Gas PipingInstall Additional Regulator if Required Connect the Supply Gas LineInstall the Drain Line Installation Evaporative Cooler Piping optionalInstall the Water Supply Line Check/Adjust Water LevelInstall Normally Open Drain Line/ Solenoid Installation of Water WizardTM optionalInstall Normally Closed Supply Line/ Solenoid Water Wizard Valves When provided by manufacturerWire the Solenoids Installation of Water WizardInstallation Direct Expansion DX Coil Piping optional Wire the Temperature SensorCheck Coil Piping for Leaks Install Suction LineMount the Remote Sensing Bulb By Others Evacuate and Charge the CoilInstallation of Chilled Water Coil Piping optional Installation of Building Pressure Control optionalStart-Up Blower Set-up Optional Components Start-Up Single Stage Control Reset the Temperature SettingStart-Up Furnaces all units Send Unit to High FireSend Unit to Low Fire Start-Up 21 Staged ControlStart-Up 81 Staged Control Check the Low Fire Manifold PressureEdit the Setting Access the Setpoints MenuAccess the Discharge Air Temperature Setting Access the Inlet Air Sensor SettingAccess the Room Override Setting High Fire Adjustment Start-Up 21 Electronic ModulationStart-Up 41 Electronic Modulation Exit High Fire ModeCheck the Low Fire Manifold Pressures Access the Setpoints Menu Set Minimum Outside Air Verify Sensor InstallationStart-Up Economizer optional Set the Enthalpy Changeover Set Point optionalStart-Up Evaporative Cooling optional Start-Up Water Wizard optional Operation - Water Wizard optional Check Operation VAV Units optional External Signal a variableBuilding Pressure Control Building Pressure Control a Check Operation Recirculating Units optionalRecirculation Operation Damper actuator may take a fewSequence of Operation Staged Sequence Exhaust Fan Contact S1 Manually Closed optionalSequence of Operation 21 Modulation Sequence Sequence of Operation Modulation Sequence Discharge Air Temperature dtSOutside Air Temperature OAt Operation Modulation Staged ControllerOptional Room Override ROt Sequence of Operation 41 Electronic ModulationProgram Revision Number Light Off BlinkingSequence of Operation Electronic Modulation Sequence of Operation Staged Control Staging Control Sequence of OperationOperation and Errors Ignition Controller Following are the green LED codes of operationOperation Economizer Option EC-1 Outside Air Temperature ReferenceOption EC-3 Differential Temperature Control Option EC-2 Outside Air Enthalpy ReferenceTroubleshooting Blower Does Not OperateMotor Over Amps Insufficient Airflow Too Much AirflowExcessive Noise or Vibration Single or 21 Stage Furnace Will Not Light Improper manifold pressureModulating Furnace Will Not Light Heat transformer TR2 fault Ignition controllers IC# failed Staged Furnace Will Not Light Internal high limit tripped temperature above set point Evaporative Cooler does not Operate Recirculating pump Water Blows through Evaporative CoolerAdjust the On Time Factor Adjust the Manual Supply ValveWater Wizard Improper Water Supply Snow Accumulation Maintenance RoutineBelt Drives WheelsChilled Water Coils MotorsFilters Evaporative CoolersMaintenance Fall Flushing Coils Reference Model IG Venting Connection Location Reference Model IGX Venting Connection LocationReference Model IG Single or 2 Stage Reference Model IG Staged Reference Model IG Modulation Modulating Reference Model IGX Blower Control Center Manifold Gas Pressure Test Port Staged Inch Gas Supply Manifold Gas Pressure Test Port Modulating Staged Reference Performance Table Performance TableReference Start-Up Checklist Start-Up ChecklistMaintenance Log Warranty