C.Preparation for Use with Various Gases

Before proceeding to set up the oven for a specific gas, check that the main gas supply valve and the circuit breaker/fused disconnect are in the OFF ("O") position.

The main and pilot orifices must match the sizes shown in the Gas Orifices and Pressure Specifications table, near the beginning of this Section. If necessary, replace the orifices. Refer to Part D, Replacing the Gas Orifices.

The orifice (manifold) pressure should be adjusted to the value shown in the Gas Orifices and Pressure Specifications table for the specific gas type and location.

1.For Use with Natural Gas

The actual heat input to the oven must match the rated heat input. The input to the burner can be determined using the orifice (manifold) pressure data or by the volume supplied using the gas meter. Both of these procedures are described in Part F, Adjusting the Orifice (Manifold) Pressure and Heat Input.

If the measured input does not correspond with the rated input (shown in the Gas Orifices and Pressure Specifications table), check first that the correct orifices are installed. If the orifices are correct, check and correct the supply and orifice pressures to obtain the correct input based on the gas meter reading.

2.For Use with Liquid Propane (LP) Gas

When using liquid gas, the converter in the multifunction gas valve must be removed, and then replaced INVERTED from its former position. See Figure 2-16. Inverting the converter will disable the governor. This step is only required if the supply pressure is below 50mbar.

Figure 2-17 - Replacing the Main and Pilot Orifices

Venturi

assembly

Pilot

orifice

 

 

Compression

 

 

nut

 

 

Pilot tube

 

 

Main

 

 

orifice

Ignition

 

Main orifice

sensor

 

holder (attached

wire

Venturi

to gas train)

 

mounting

 

 

plate

 

SECTION 2 - INSTALLATION

D.Replacing the Gas Orifices (if so required)

1.Replacing the Main Orifice

a.Check that the main gas supply valve and the circuit breaker/fused disconnect are in the OFF ("O") position.

b.Open the union in the gas supply line. The union is shown in Figure 2-16, on the previous page.

c.Refer to Figure 2-17. Unscrew the four hex screws that hold the venturi mounting plate to the front of the burner. Remove the gas train/venturi assembly from the oven.

d.Remove the two 1/2" nuts that secure the gas train to the venturi mounting plate.

e.Remove the main orifice using an 11/16" wrench.

f.Install the new orifice.

2.Replacing the Pilot Orifice

NOTE: All natural gases use the same size pilot orifice (0,635mm), as do all liquid propane (LP) gases (0,381mm). Because of this, it is not normally necessary to replace the pilot orifice unless converting the oven from natural to propane, or from propane to natural, operation.

a.Refer to Figure 2-17. Unscrew the pilot tube compression nut and slide it out of the way. Pull the tube from the fitting to expose the pilot orifice.

b.Remove the pilot orifice.

c.Slip the new pilot orifice into the pilot tube.

d.Push the pilot tube back into place until it bottoms, and hold it in place. Slide the compression nut back into place and engage the threads. Tighten the nut to a snug fit with your fingers.

e.Gently tighten the nut one complete turn with a wrench.

DO NOT OVERTIGHTEN THE COMPRESSION NUT.

3.Replacing the Bypass (Low Flame) Orifice

a.Refer to Figure 2-16. Note the locations of the 1/2" hex compression nuts that hold the bypass line in place. Loosen the compression nuts using a 1/2" wrench.

b.Remove the bypass tube. Then, remove the bypass orifice from the tube.

c.Slip the new orifice into the bypass tube.

d.Replace the tube onto its fittings on the solenoid valve. While holding the tube in place, slide the compression nuts back into place and engage the threads. Tighten the nut to a snug fit with your fingers.

e.Gently tighten the nuts one complete turn with a wrench.

DO NOT OVERTIGHTEN THE COMPRESSION NUTS.

f.Replace the gas train and venturi by following Steps a- d in Replacing the Main Orifice, above, in reverse order.

WARNING

After completing these procedures, perform a gas leak test before operating the oven.

ENGLISH

13

Image 13
Contents PS360WB PS360English For Your SafetyTable of Contents Description English III. Oven SpecificationsOven Uses II. Oven Components see FigureElectrical specifications per oven cavity InstallationGas orifice and pressure specifications per oven cavity Installation kit components one kit required per cavity Installation KITAdditional installation kit components for gas ovens 710Requirements II. Ventilation SystemRecommendations Other ventilation concernsIV. Thermocouple Installation III. AssemblyRemoving the Conveyor Drive Sprocket Conveyor Installation11 Conveyor and Master Link Orientation VI. Final AssemblyVII. Electrical Supply DURINGPRESSURETESTINGNOTEONEOFTHEFOLLOW- INGVIII. GAS Supply Gas Meter Gas Utility Rough-In RecommendationsGas Line Replacing the Gas Orifices if so required Preparation for Use with Various GasesVolumetric Method Adjusting the Orifice Manifold Pressure and Heat InputChecking the Gas Supply Inlet Pressure Orifice Manifold Pressure MethodReset Switch Gas ovens only. Illuminates Conveyor Switch Turns the conveyor drive motor on and offOperation Location and Description of ControlsDailyshutdownprocedure DailystartupprocedureII. Normal Operation STEP-BY-STEP III. Quick Reference Digital Temperature Controller Symptom IV. Quick Reference TroubleshootingMaintenance Daily MaintenanceRemoving the Conveyor II. Maintenance MonthlySplit Belt Disassembly and Cleaning III. Maintenance Every 3 MonthsKEY Spare Parts KIT Available sepa- rately. See Figure IV. Maintenance Every 6 MonthsDescription 400V, 50 Hz, 1 Ph DiagramsImportant also located inside An electrical wiring diagram for the oven isCompartment Gas OvenReguleret opvarmningszone Regulerede opvarmningszoner PS300 serien gas- og elektriske ovneMeddelelse DanskIndholdsfortegnelse AFSNIT5-LEDNINGSDIAGRAMMERAfsnit 3 Betjening AFSNIT4-VEDLIGEHOLDELSEOvnens Anvendelsesmuligheder Afsnit 1 Beskrivelse DanskII. Ovnkomponenter se Figur III. OvnspecifikationerTabel 1-3 Generelle specifikationer pr. ovnhulrum Afsnit 2 InstallationTabel 1-4 Specifikationer for gasåbning pr. ovnhulrum Yderligere komponenter til installationssæt til gasovne InstallationssætEnhed Beskrivelse Delnummer ØversteovnKrav II. VentilationssystemAnbefalinger Andre ventilationsanliggenderIII. Montering IV. Installation AF TermoelementDansk Installation AF TransportbåndBemærk 11 Transportbånds- og samleledsretning VI. Endelig MonteringVIII. Gasforsyning Forsigtig VII. StrømforsyningUnder Trykprøvning Skal ET AF Følgende Bemærkes Gasudsivningstest, før ovnen betjenes Udførelse af disse procedurer, skal Der UdføresUdskiftning af gasåbninger hvis det kræves Forberedelse til brug med forskellige gastyperKontrol af gasforsyningstrykket indgang Volumetrisk metodeJusteringen af åbningens tryk manifold og varmetilførsel Åbningstrykmetoden manifoldPlacering OG Beskrivelse AF Betjeningsknapper Afsnit 3 BetjeningHeat varme kontakt Tillader at brænder Daglignedlukningsprocedure DagligopstartprocedureII. Normal Betjening Trin for Trin III. Hurtig Reference Digital Temperaturregulator IV. Hurtig Reference Fejlfinding Bemærk Afsnit 4 VedligeholdelseVedligeholdelse Dagligt ForsigtigEksempler på markeringer II. Vedligeholdelse MånedligAfmontering og rengøring af dobbeltbånd III. Vedligeholdelse Hver 3. MånedNøgle Reservedelssæt fås separat. Se figur IV. Vedligeholdelse Hver 6. MånedEnhed Del nr Beskrivelse Afbrydere 380-400V, 50 Hz, 1 faseMaskinkassen Der findes også et ledningsdiagramPS360-U/-L eller Gasovn, 220-230V, 50Hz