Installation of hanging bolts

RAV-SM561, 801CT-E RAV-SM1101, 1401CT-E

Installation of hanging bolts

Use M10 hanging bolts (4 pcs, to be local procure). Matching to the existing structure, set pitch according to size in the unit external view as shown below.

New concrete slab

Install the bolts with insert brackets or anchor bolts.

 

 

Rubber

 

 

Anchor bolt

(Blade type

(Slide type

(Pipe hanging

bracket)

bracket)

anchor bolt)

Pipe knockout hole

In case of taking pipe from the rear side

*Cut off the groove section with a plastic cutter, etc.

Pipe knockout hole Rear cover

•In case of taking pipe from the rear side100

Opened when refrigerant pipe is taken out from the rear side

Grooves

Opened when only drain pipe is taken out from the rear side

Steel flame structure

Use existing angles or install new support angles.

•In case of taking pipe from right side Hanging bolt

Hanging bolt

Support angle

Existing concrete slab

Use a hole-in anchors, hole-in plugs, or a hole-in bolts.

In case of taking pipe from right side

*Cut off the groove section with a metal saw or plastic cutter, etc.

Groove

Side panel (Right)

In case of taking pipe from left side

Taking pipe from left side is applied only to the drain pipe.

The refrigerant pipe cannot be taken out from the left side.

*Cut off the groove section with a metal saw or plastic cutter, etc.

Draw-out direction of pipe/cable

Decide installation place of the unit and draw-out direction of pipe and cable.

Knockout hole of power cable take-in port

Open the power cable take-in port (Knockout hole) shown in the external view and then mount the attached bushing.

Groove

Side panel (Left side))

In case of taking pipe from upper side

Taking pipe from upper side is applied only to the refrigerant pipe.

When taking out the drain pipe from the upper side, use a drain up kit sold separately.

Open the upper pipe draw-out port (Knockout hole) shown in the external view.

(Knockout hole of thin plate)

After piping, cut off the attached thermal insulator of the top plate to pipe shape, and then seal the knockout hole.