Installation Instructions

IM584000300

Spec. No. 584000300 (Model 4015-X003)

Issue AB, April 3, 2013

 

 

INSPECTING THE EQUIPMENT AND

STORING FOR DELAYED INSTALLATIONS

Inspecting the Equipment

Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and your local Emerson representative immediately.

While the DC Power System is still on the truck, inspect the equipment and shipping container(s) for any signs of damage or mishandling.

As the equipment is moved off the truck and unpacked, visually examine the DC Power System for transit damage.

Do not attempt to install the system if damage is apparent.

If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact Emerson Network Power (number located on last pages of this document) to inform them of the damage claim and the condition of the equipment.

Storing for Delayed Installation

If the equipment will not be installed immediately, it must be stored indoors where the humidity is no higher than 95%. The storage area must protect the DC Power System from excessive moisture.

SECURING THE IT RACK TO THE FLOOR

Secure the IT rack to the floor per site requirements. Refer also to the General

Requirements section at the beginning of this chapter.

Factory Integrated Systems (List R1, R2)

For systems factory furnished in an IT rack (List R1, R2), position and secure the

Emerson Network Power DCM IT Rack to the floor as follows.

Procedure

1)Use at least two people when moving the IT rack.

2)Using a pallet jack or forklift, move the IT rack on its pallet to the installation location.

3)Cut the shrink wrap and remove all packaging.

4)Remove the lag bolts securing each shipping bracket to the shipping pallet. There is one bracket at each corner of the IT rack (each bracket has two lag bolts).

5)Use a pallet jack or forklift to raise the IT rack off the shipping pallet.

6)Slide the shipping pallet out from under the IT rack.

7)The IT rack may be positioned for installation either with the forklift or by rolling the cabinet on its casters. If the casters are to be used to move the cabinet, prepare the IT rack for rolling as follows.

a)Set the IT rack on the floor.

b)Using a hex wrench, lower each leveling feet until the IT rack is not resting on the shipping brackets.

c)Remove the hex bolts securing each shipping bracket to the IT rack.

Chapter 2. Installing the System

Page 9

This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy

Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.

Page 19
Image 19
Emerson 4015 Inspecting the Equipment Storing for Delayed Installations, Securing the IT Rack to the Floor