IM584000300

Installation Instructions

Issue AB, April 3, 2013

Spec. No. 584000300 (Model 4015-X003)

 

 

INSTALLATION ACCEPTANCE CHECKLIST

General

The individual components of the DC Power System may be shipped as a complete solution factory installed and wired in an IT rack, or may be shipped separately to be installed in a customer provided IT rack.

Provided next is an Installation Acceptance Checklists for each option:

Factory Integrated System (List R1, R2)

Customer Integrated System (ship loose)

These Installation Acceptance Checklists help ensure proper installation and initial operation of the system. As the procedures presented in Chapters 2 through 5 of this document are completed, check the appropriate box on the appropriate Installation Acceptance Checklist. If the procedure is not required to be performed for your installation site, also check the box to indicate that the procedure was read. When installation is done, ensure that each block in the appropriate Installation Acceptance Checklist has been checked. Some of these procedures may have been factory performed for you.

Note: The system is not powered up until the end of the Installation Acceptance

Checklist.

Note: Some of these procedures may have been performed at the factory for you.

Checklist –Factory Integrated System (List R1, R2)

Chapter 2. Installing the System

Equipment Inspection Completed

IT Rack Secured to Floor

Chapter 3. Making Electrical Connections

IT Rack Grounding Connection (Frame Ground) Made

AC Input Power and AC Input Equipment Grounding Connections Made

DC Load Distribution Connections to List 21-24 Distribution Sub-Rack(s) Made (if furnished)

Battery Sub-Trays Installed in List 91-92 Battery Tray(s) (if furnished)

External Battery Connections Made (if required)

IB2 (ACU+ Controller Interface Board) Connections Made (if required)

ACU+ Controller Ethernet Connection Made (if required)

Power and Control Sub-Rack Bulk Output Connections Made (if required)

Chapter 4. Installing the Rectifiers

Rectifiers Installed

Chapter 5. Initially Starting the System

System Started, Configured, and Checked

Page 6

Chapter 1. General Information and Installation Acceptance Checklist

This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy

Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.

Page 16
Image 16
Emerson 4015 Installation Acceptance Checklist, General, Checklist -Factory Integrated System List R1, R2