e.Display Controls
To adjust the display parameters, from the Main menu choose “Display con- trols…” as follows:
| TO2 |
|
|
|
|
|
|
| 37.50 ppm | ||||
|
|
|
|
|
|
|
|
|
| ||||
|
| Analyzer basic controls (calibration) & setup… |
|
|
| ||||||||
|
| Analyzer and I/O, expert controls & setup… |
|
|
| ||||||||
|
| System configuration and diagnostics… |
|
|
|
| |||||||
|
|
|
|
|
|
|
|
|
|
| |||
|
| Display controls… |
|
|
|
|
|
|
|
| |||
|
|
|
|
|
|
| |||||||
|
| Time & Date: |
|
| 06:34:25 February 01 2000 | ||||||||
|
| System tag: |
|
|
|
|
| ||||||
|
| Measure |
|
| Status… |
| Channel |
|
| Lock… |
| MFG Data | |
|
|
|
|
|
|
|
|
|
| ||||
| TO2 |
|
|
|
|
|
| 37.50 ppm | |||||
|
|
|
|
|
|
|
|
| |||||
|
|
|
|
|
|
|
|
|
|
| |||
|
| Brightness: |
|
|
|
|
|
| 70 % |
| |||
|
| Contrast: |
|
|
|
|
|
| 23 % |
| |||
|
| Switch automatically to “Measure” after: |
|
| 30 s | ||||||||
|
| Switch off backlight after: |
|
| Never | ||||||||
|
|
|
|
|
|
|
|
|
|
|
| ||
|
| Measure |
|
|
|
|
|
|
| Back… |
|
|
|
From the Main menu, move the cursor to the “Display controls…” line and press the ↵ key. The menu will display as shown below.
Brightness and Contrast:
These controls can be adjusted to accom- modate the ambient lighting conditions. The range of values are
These values can be reset to the defaults from the Multi Channel display screen (F1 from the “Measure” screen) by pressing F5 (LCDReset). It can also be reset from the startup screen by pressing F1 (see Figure
Figure 3-14. Display Controls
NOTE:
It is possible to change the brightness and contrast values do that the display is no longer visible. In such case, press the F1 key twice to change to the multi component display and then press the F5 key for LCDReset.
Switch automatically to “Meas- ure” after:
This variable line allows setting of the delay time before any selected menu switches back to the Measure screen. The selectable values are:
5sec
10sec
30sec
1min
5min
30min Never