Baldor GLC25, GLC10, GLC60 Example Determining Pipe Size for Natural Gas, Natural Gas Connections

Page 31

Example: Determining Pipe Size for Natural Gas

A generator has a 16Hp engine 60 feet from the supply. Determine the supply pipe size for Natural Gas fuel.

16 x 10,000 = 160,000 BTU's / per hour for proper operation. 160, 000

1, 096

+ 146cubicfeetperhour.

From Table 3‐6, a 60 foot run requires a minimum 1” pipe at full engine load.

Natural Gas Connections

The incoming pressure must be 11 inches water column (6 oz. pressure).

Table 3‐5 Natural Gas Flow Rate (Cubic Feet per Hour) per Pipe Length

Pipe

 

 

 

 

 

Iron Pipe Size

 

 

 

 

 

Length

 

 

 

 

 

 

 

 

 

 

 

 

 

1/

3/

1

1- 1/

1- 1/

 

2

 

2- 1/

3

4

6

8

(Feet)

 

 

2

4

 

4

2

 

 

 

2

 

 

 

 

15

73

165

332

722

1174

 

2386

 

3704

6253

13352

37229

 

30

50

115

232

515

818

 

1712

 

2646

4521

9331

26330

53728

45

41

95

191

418

673

 

1419

 

2213

3752

7600

22462

43867

60

37

83

166

366

587

 

1241

 

1924

3319

6542

18595

37999

75

 

74

149

332

524

 

1077

 

1684

2886

5772

16652

33959

90

 

67

137

298

433

 

962

 

1501

2597

5291

15200

31025

105

 

63

126

274

 

 

885

 

1376

2357

4906

14064

28715

120

 

 

115

260

404

 

827

 

1289

2213

4618

13160

26859

150

 

 

105

233

366

 

750

 

1174

2011

4185

11775

24050

180

 

 

96

216

337

 

693

 

1077

1876

3848

10736

21934

210

 

 

89

197

308

 

635

 

991

1712

3559

9937

20298

240

 

 

 

183

289

 

596

 

933

1616

3357

9235

18990

270

 

 

 

171

274

 

558

 

875

1520

3127

8658

17903

300

 

 

 

164

260

 

524

 

827

1433

2886

8177

16998

Note: Almost all operation problems are related to the installation techniques used. Do Not guess, be sure pipe size is adequate for required flow rate.

1.Connect the proper size gas pipe at the Inlet Connection to the Fuel Lock Solenoid. Connect the Natural Gas pipe line shown in Figure 3‐3 using the correct size pipe for the required flow rate and length of pipe. Refer to Table 3‐5 for pipe size. Be certain that all connections are sealed and no leaks are present. The installer must ensure that all gas connections comply with all building codes.

2.Verify Fuel Supply Pressure

Prior to initial operation of generator, verify that fuel system pressure is 11Water Column (6 oz. pressure) and fuel pipe sizes comply with Table 3‐5.

3.Proceed to Electrical Connections.

Figure 3‐3 Gas Line Connections

Air Cleaner

Carburetor

Solenoid, Fuel Lock

Inlet Connection

Mounting Bracket

External Supply Piping (by installer)

U.L. requires a second shutoff valve and regulator to be installed in the supply piping to control the gas supply to the generator.

To Inlet

Supply Piping

 

Connection

 

Additional Regulator

Additional Valve

(11 - 14” water column pressure)

(Safety Shutoff Valve)

MN2408

Receiving & Installation 3‐7

Image 31
Contents MN2408 GLC GeneratorCalifornia Proposition 65 Warning Table of Contents Appendix a Troubleshooting and Maintenance Problems and SolutionsAppendix B Read This Manual Thoroughly Section Product Safety InformationOperation SymbolsOperation Warning Statements Burn Installation Battery Safety Maintenance Generator Series Labor Parts Limited WarrantyWarranty Period Any warranty coverage‐2 General Information MN2408 Site Planning Installation GuidelinesRoom Air Controls and Transfer SwitchEngine Cooling System Exhaust SystemSetting The Genset On An Existing Concrete Floor Slab Foundation Design Foundation ChecklistVibration Isolators ‐2 Approximate Weight vs. kW Output Weight Of The Genset‐3 Calculate Soil Bearing Load SBL Capacity Designing An Isolated FoundationSoil Type Safe Bearing Capacity Lb per ft Kilo Pascals ‐5 Typical Foundation InstallationExhaust System ‐6 Exhaust System Calculations Exhaust Piping Transfer Switch Checklist Transfer SwitchTransfer Switch Location Battery Location Battery Starting SystemBattery Cables Battery Charger‐14 General Information MN2408 ‐1 Generator Lifting When the Generator is installed outdoorsSound ‐2 Mounting Dimensions‐3 Stub Up Detail Generator OpenVentilation Test Secure the GeneratorBackpressure must not exceed 20 of water column Hot Exhaust GassesGuidelines for Exhaust System Page ‐4 Fuel Consumption Natural and LPV Fuel ConnectionsGeneral Considerations Pipe Iron Pipe Size Length External Supply Piping by installerExample Determining Pipe Size for Natural Gas Natural Gas Connections‐6 LP Vapor Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for LPVCatalog No Rating Single Phase Power Connections Transfer Switch ConsiderationsRemote Start Neutral L1L2 Connections AC Power Connections GroundConnections General Wiring Considerations Battery Charger ConsiderationsGLC125 Recommended Engine Oil and Battery TypeGLC10-25 GLC100Post Installation Checks Post Installation Checks ‐16 Receiving & Installation MN2408 Digital Engine Controller Description EM0046A21 MRS17 ‐8 Alarm & Warning ConditionsDigital Engine Controller Description EM0046A21 MRS17 OFF ModeMAN Mode AUT ModeMenu Status Condition of Transition Action  Next State Adjustment MenuAlarm List ECU Alarm List‐10 Possible Warnings AlarmsSensor fail FLS see ‐10 Shut down SD see ‐10Used for shunt trip Inputs and Outputs‐11 Binary Inputs ‐12 Binary outputs‐13 Analog Inputs Set points‐14 Basic Setpoints ‐15 Engine Setpoints During the first 500ms. ,1s Range 0 3s Delay for Analog Input 2 Wrn Wtemp low. s Range1-180 s‐15 Engine Setpoints ‐16 Engine Protect Setpoints‐17 Generator Protect Setpoints ‐19 IOM/PTM Module Setpoints ‐18 Sensor Spec Setpoints‐11 Controller Connection Diagram Jdic OFF Switch Alarm LEDSpeed Signal LED Run SwitchManual Start/Stop Operator Control PanelAutomatic Start/Stop Automatic Mains Failure AMF Automatic Fault ShutdownLoad Test Push-button Operation Utility Power Failure ConditionsUtility Power Restored Utility Normal ConditionNo Load Test Internal FaultsDigital Input Faults Fault Digital Inputs Name Action Terminal #‐15 Engine Controller Inputs & Outputs Fault Inputs Name Action Signal Analog FaultsFail Programmable Contacts Such as Fuel Rack Solenoids or electronic governorsCrank Engine starter motorAction Description Display Comments Name and remaining time Apply Power Main LCD DisplayReset faults Show Operating Status screensGenerator Average Output Display Generator Phase Voltage Display Line to LineGenerator Phase/Neutral Voltage Display Line to Neutral Generator Phase Current DisplayProgram Menus Navigation Hints Main Menu Loop Zero Calibration Voltage Calibration ProcedureSpan Calibration Repeat for each phaseDisplayed values Displays the type of calibration function Engine Temperature & Oil Pressure CalibrationOil Pressure ‐16 Configuration Data Sheet Toggle Between Psi/Kpa Parameter Setting RangeSystem Voltage Line To Line 120-15000V ACParameter Setting ‐21 Engine Control Connections ‐34 Operation MN2408 Engine General‐1 General Troubleshooting Guide Problems and SolutionsProblem Possible Cause Remedy ‐2 Troubleshooting Guide Digital Controller Only Service ‐3 Troubleshooting Guide Analog Controller OnlyVerify the adjustments. Replace controller if failed Options & Accessories A‐1 Battery ChargerInstallation Considerations BatteryFigure A‐2 Battery Heating Pad Installation BTHTR81 Heater Engine Block Heater Options & Accessories A‐3GLC10-25 GLC30-45 GLC60-90 GLC100-105 SilencersFuel Strainers & Fuel Lines Options & Accessories A‐5Fuel Strainer Stop Figure A‐6 InstallationRemote Annuciators Options & Accessories A‐7GLC80-100 Radiator Duct FlangeGenerator GLC30-60GLC60-90 H1=64.2, H2=76.8 Options & Accessories A‐9Enclosures GLC10-25 H1=36.0 L1=11.75 GLC30-45 H1=52.1, H2=66.6‐10 Series GLC MN2408 Series GLC B‐1 Qty per PhaseGLC Circuit Breaker & Electrical Data OSH PlantFigure B‐11 Customer Interface Connection Diagram Series GLC B‐3 Figure B‐13 Single Phase w/o Breaker Connection Diagram Series GLC B‐5 Figure B‐14 Single Phase One Breaker Connection DiagramFigure B‐15 Single Phase Two Breaker Connection Diagram Series GLC B‐7 ‐8 Series GLC MN2408 Series GLC B‐9 ‐10 Series GLC MN2408 Series GLC B‐11 Figure B‐20 Three Phase Connection DiagramFigure B‐21 Three Phase Connection Diagram with PMG Series GLC B‐13 ‐14 Series GLC MN2408 Series GLC B‐15 ‐16 Series GLC MN2408 Series GLC B‐17 Figure B‐27 Control Box Connections with MEC20 Controller Series GLC B‐19 Figure B‐29 Control Box Connections with MEC2 Controller Series GLC B‐21 Figure B‐30 Engine Wiring, Woodward 4.3L GMFigure B‐31 Engine Wiring, Woodward 5.7L GM Series GLC B‐23 Figure B‐32 Engine Wiring, Woodward 8.1L GM‐24 Series GLC MN2408 Baldor District Offices Baldor Electric Company MN2408