Battery Charger Considerations

1.Mount the battery charger on the generator or as close to the generator as possible.

2.If you mount the battery charger inside the building, mount it near the main breaker box or disconnect box.

3.If you mount the battery charger outside, you must protect it from the environment and the elements.

4.Do not mount the battery charger where flammable liquids or vapors are present.

General Wiring Considerations

1.When routing the interface wiring, do not route it up against anything that could cut or chafe the wiring. do not route the wire up against any hot or potentially hot object.

2.Make sure that all the electrical components (generator set, transfer switch, battery charger, etc.) share a common hard wired ground.

3.Check with your local building inspector to determine what you must do to comply with the local regulations for grounding of this type of permanent installation.

3‐12 Receiving & Installation

MN2408

Image 36
Contents GLC Generator MN2408California Proposition 65 Warning Table of Contents Troubleshooting and Maintenance Problems and Solutions Appendix aAppendix B Section Product Safety Information Read This Manual ThoroughlySymbols OperationOperation Warning Statements Burn Installation Battery Safety Maintenance Limited Warranty Warranty PeriodAny warranty coverage Generator Series Labor Parts‐2 General Information MN2408 Installation Guidelines Site PlanningControls and Transfer Switch Engine Cooling SystemExhaust System Room AirFoundation Design Foundation Checklist Setting The Genset On An Existing Concrete Floor SlabVibration Isolators Weight Of The Genset ‐2 Approximate Weight vs. kW OutputDesigning An Isolated Foundation ‐3 Calculate Soil Bearing Load SBL Capacity‐5 Typical Foundation Installation Soil Type Safe Bearing Capacity Lb per ft Kilo PascalsExhaust System ‐6 Exhaust System Calculations Exhaust Piping Transfer Switch Transfer Switch ChecklistTransfer Switch Location Battery Starting System Battery LocationBattery Charger Battery Cables‐14 General Information MN2408 When the Generator is installed outdoors ‐1 Generator Lifting‐2 Mounting Dimensions ‐3 Stub Up DetailGenerator Open SoundSecure the Generator Ventilation TestHot Exhaust Gasses Backpressure must not exceed 20 of water columnGuidelines for Exhaust System Page Fuel Connections ‐4 Fuel Consumption Natural and LPVGeneral Considerations External Supply Piping by installer Example Determining Pipe Size for Natural GasNatural Gas Connections Pipe Iron Pipe Size LengthExample Determining Pipe Size for LPV ‐6 LP Vapor Flow Rate Cubic Feet per Hour per Pipe LengthCatalog No Rating Transfer Switch Considerations Single Phase Power ConnectionsRemote Start AC Power Connections Ground Neutral L1L2 ConnectionsConnections Battery Charger Considerations General Wiring ConsiderationsRecommended Engine Oil and Battery Type GLC10-25GLC100 GLC125Post Installation Checks Post Installation Checks ‐16 Receiving & Installation MN2408 ‐8 Alarm & Warning Conditions Digital Engine Controller Description EM0046A21 MRS17OFF Mode MAN ModeAUT Mode Digital Engine Controller Description EM0046A21 MRS17Adjustment Menu Alarm ListECU Alarm List Menu Status Condition of Transition Action  Next StateAlarms Sensor fail FLS see ‐10Shut down SD see ‐10 ‐10 Possible WarningsInputs and Outputs ‐11 Binary Inputs‐12 Binary outputs Used for shunt tripSet points ‐13 Analog Inputs‐14 Basic Setpoints ‐15 Engine Setpoints Delay for Analog Input 2 Wrn Wtemp low. s Range1-180 s ‐15 Engine Setpoints‐16 Engine Protect Setpoints During the first 500ms. ,1s Range 0 3s‐17 Generator Protect Setpoints ‐18 Sensor Spec Setpoints ‐19 IOM/PTM Module Setpoints‐11 Controller Connection Diagram Jdic Alarm LED Speed Signal LEDRun Switch OFF SwitchOperator Control Panel Manual Start/StopAutomatic Start/Stop Automatic Fault Shutdown Automatic Mains Failure AMFUtility Power Failure Conditions Utility Power RestoredUtility Normal Condition Load Test Push-button OperationInternal Faults Digital Input FaultsFault Digital Inputs Name Action Terminal # No Load Test‐15 Engine Controller Inputs & Outputs Analog Faults Fault Inputs Name Action SignalSuch as Fuel Rack Solenoids or electronic governors CrankEngine starter motor Fail Programmable ContactsAction Description Display Comments Apply Power Main LCD Display Reset faultsShow Operating Status screens Name and remaining timeGenerator Phase Voltage Display Line to Line Generator Phase/Neutral Voltage Display Line to NeutralGenerator Phase Current Display Generator Average Output DisplayProgram Menus Navigation Hints Main Menu Loop Voltage Calibration Procedure Zero CalibrationRepeat for each phase Span CalibrationDisplayed values Engine Temperature & Oil Pressure Calibration Displays the type of calibration functionOil Pressure ‐16 Configuration Data Sheet Parameter Setting Range System Voltage Line To Line120-15000V AC Toggle Between Psi/KpaParameter Setting ‐21 Engine Control Connections ‐34 Operation MN2408 General EngineProblems and Solutions ‐1 General Troubleshooting GuideProblem Possible Cause Remedy ‐2 Troubleshooting Guide Digital Controller Only ‐3 Troubleshooting Guide Analog Controller Only ServiceVerify the adjustments. Replace controller if failed Battery Charger Installation ConsiderationsBattery Options & Accessories A‐1Figure A‐2 Battery Heating Pad Installation BTHTR81 Heater Options & Accessories A‐3 Engine Block HeaterSilencers GLC10-25 GLC30-45 GLC60-90 GLC100-105Options & Accessories A‐5 Fuel Strainers & Fuel LinesFuel Strainer Figure A‐6 Installation StopOptions & Accessories A‐7 Remote AnnuciatorsRadiator Duct Flange GeneratorGLC30-60 GLC80-100Options & Accessories A‐9 EnclosuresGLC10-25 H1=36.0 L1=11.75 GLC30-45 H1=52.1, H2=66.6 GLC60-90 H1=64.2, H2=76.8‐10 Series GLC MN2408 Qty per Phase GLC Circuit Breaker & Electrical DataOSH Plant Series GLC B‐1Figure B‐11 Customer Interface Connection Diagram Series GLC B‐3 Figure B‐13 Single Phase w/o Breaker Connection Diagram Figure B‐14 Single Phase One Breaker Connection Diagram Series GLC B‐5Figure B‐15 Single Phase Two Breaker Connection Diagram Series GLC B‐7 ‐8 Series GLC MN2408 Series GLC B‐9 ‐10 Series GLC MN2408 Figure B‐20 Three Phase Connection Diagram Series GLC B‐11Figure B‐21 Three Phase Connection Diagram with PMG Series GLC B‐13 ‐14 Series GLC MN2408 Series GLC B‐15 ‐16 Series GLC MN2408 Series GLC B‐17 Figure B‐27 Control Box Connections with MEC20 Controller Series GLC B‐19 Figure B‐29 Control Box Connections with MEC2 Controller Figure B‐30 Engine Wiring, Woodward 4.3L GM Series GLC B‐21Figure B‐31 Engine Wiring, Woodward 5.7L GM Figure B‐32 Engine Wiring, Woodward 8.1L GM Series GLC B‐23‐24 Series GLC MN2408 Baldor District Offices Baldor Electric Company MN2408