Extron electronic 305SA manual Secure the Projector Drop Ceiling Mount to the Ceiling

Page 22

7.— Secure the Projector Drop Ceiling Mount to the Ceiling

a.Attach the four turnbuckles to the mounting plate, one at each corner.

WARNING: May result in serious injury.

DO NOT rest or lean on the mounting

plate or suspended ceiling when attaching

turnbuckles, tie wire, or when drilling into

the ceiling.

NOTE: For safest installation, insert the

turnbuckle from the outside so that it

hooks inwards

b.Cut four equal lengths of the supplied hanging wire, and loop the wire through the anchors or lag eye bolts, and the turnbuckles, then twist the wire around itself at least five times tightly at each end.

c.Hand tighten the turnbuckles and level the plate so it just rests on the T-frame.

CAUTIONS:

The four hanging wires should be taut, taking the full weight of the completed installation.

Do not overtighten the turnbuckles or the Tframe assembly could be lifted, making the suspended ceiling bowed and unsafe

e.Pass the braided safety cable through the fifth and center anchor and attach it to the center holes on either side of the plate. Ensure the cable is of equal length on both sides of the anchor and secure the cable using the cable clamps.

ÅAttach the turnbuckles at the corners of the PCM 340.

Secure PCM to frame (from either side)

PCM

T-frame

Adjust the turnbuckles to take up any slack in the hanging wire.

K Hand tighten all four turnbuckles.

18PoleVault IP Systems • Installation — Stage 1 (Screen and Projector)

Image 22
Contents PoleVault IP Systems Safety Instructions Sicherheitsanweisungen DeutschFCC Class B Notice Guide on the Extron websiteLetter o Specifications AvailabilityConventions Used in this Guide Variables are written in slanted form as shown hereOverview PoleVault IP SystemPoleVault IP System Installation and Wiring Overview Before You Begin Planning the Installation Typical Classroom InstallationLocation of the Screen and Projector Location of MediaLink Controller and Wall Plates Inventory Included ItemsKits See rear cover for contact numbersItems Not Included Installation Overview Outline of Installation Steps Stage Installing the Screen Projector Mark the screen location Install Projector to Verify LocationMark Screen Location Place the PCM 340 on the T-barScrew the adjuster plate onto the base of the pipe Viii. Evenly balanced configuration Using the slots on the bracket that areClosest to the barrel on each arm, place Slide and lock the projector onto the adjuster plate Verify the Image LocationCut the Ceiling Tile Preliminary Safety Hardware InstallationMark the structural ceiling for lag eye bolt installation Take the measurements with the PCM 340 on the T-frameFinish Projector Drop Ceiling Mount Installation Attach the turnbuckles at the corners of the PCM Secure the Projector Drop Ceiling Mount to the CeilingHand tighten all four turnbuckles Install the Raco box and plaster ring onto the PCM Install the Electrical Box if requiredShock or serious injury. For safety Install the ScreenPage PVT CV D and PVT RGB D IP Plus AV Source Input Wallplates MLS 104 IP Plus MediaLink Controller PVT transmitter installationMLC 104 IP Plus installation Cabling for the Wallplates and MediaLink ControllerFeatures for MLC Mud Ring Installation Install the Mud RingsInsert the PVT mud ring into the wall Provide strain relief Signal Cable Label colorPull the cables at each location Install Wall Plates Install MediaLink Controller Connect the MLC 104 IP Plus to the switcherConnect to the LAN using a CAT 5 cable Terminal RS-232 Cable color PinConnections made to the MLC 104 IP Plus TCP/IPFF 120 Flat Field Ceiling Speakers Stage 3 Involves Installing the Devices Shown BelowSpeaker Installation Cabling for the SpeakersCut Ceiling Tile Install the Speaker on the Drop CeilingMark and cut the tile Attach safety cable Stereo or dual mono output using parallel speaker wiring Terminate the Speaker Cable for the PVS SwitcherWire the captive screw connector Stereo output Dual mono outputPMK 550 Pole Mount Kit PVS 305SA IP PoleVault SwitcherStage 4 Involves Installing the Devices Shown Below Rear ViewInstall the PMK 550 Base Plate Switcher and Projector Cable Overview Pull the Cables at the Switcher locationGather the cables, pass them down the pipe Finish installing the Pole Mount Kit Your completed connections should look like the image belowStage 5 Involves Installing the Programs Shown Below Configure the Switcher MLS Switcher Configuration ProgramConfigure the System Global ConfiguratorCheck that an image is present, and adjust as needed Test the SystemTest the MLC configuration is correct Adjust the audio levels on the PVS 305SA IPFinal Installation When the image is correct, re-install the wallplate Using Preset ModeAny changes to the Edid settings as needed Preset Switch setting Resolution NumberUsing Learn Mode Available on PVT RGB D Plus only On the rear panel, set all the DIP switches to off downInstallation Procedure Optional Accessory Installation VoiceLift SystemVoiceLift System Included parts Optional Accessory Installation Priority Page Sensor Kit Priority Page Sensor Kit Included PartsTesting and Adjustment Procedure Configuration program for MLSPoleVault Switchers PVS, available at Typical paging system with PVS 305SA IP switcherExtron Warranty Outline of Installation Steps