8. — Install the Electrical Box (if required)

WARNING: Improper installation may result in electrical shock or serious injury.

All electrical installation should be performed by qualified personnel in accordance with local and national building codes, fire and safety codes, and local and national electrical codes.

If required, the following method is recommended for integrating a 4S RACO® electrical box (not supplied) on the PCM base plate (for example, a RACO 232, 2 1/8 inch deep, 4x4 inch electrical box and a RACO 778, 1/2 inch raised, 4x4 inch plaster ring or similar).

Install the Raco box on the PCM plate as follows:

a.Attach the box to the plate, using the smallest notches in opposite corners of the cut-out (see figure 8a). Do not tighten the screws fully at this time.

b.On the opposite side of the PCM plate, slide the plaster ring under the screws. The plaster ring anchors the box in place with PCM plate sandwiched between.

c.Fully tighten the screws.

WARNING: May result in electrical

shock or serious injury. For safety,

complete all wiring of the electrical boxes

and accessories after the plate is fully

installed and secured.

RACO box

Use the smallest notches when

attaching the

RACO box.

RACO 778

ÉInstall the RACO box and plaster ring onto the PCM 340.

d.Mark and cut a hole in the ceiling tile for the electrical box opening.

9.— Install the Screen

a.Following the guidelines given by the screen manufacturer, continue to install the screen mounting brackets and then hang the screen.

TIP: Use S-hooks to hang the screen from

the brackets. Bend the ends of the S-

hooks so the screen does not fall when it

is rolled up.

PoleVault IP Systems • Installation — Stage 1 (Screen and Projector)

19

Image 23
Contents PoleVault IP Systems Sicherheitsanweisungen Deutsch Safety InstructionsGuide on the Extron website FCC Class B NoticeVariables are written in slanted form as shown here Specifications AvailabilityConventions Used in this Guide Letter oPoleVault IP System OverviewPoleVault IP System Installation and Wiring Overview Typical Classroom Installation Before You Begin Planning the InstallationLocation of the Screen and Projector Location of MediaLink Controller and Wall Plates Included Items InventorySee rear cover for contact numbers KitsItems Not Included Installation Overview Outline of Installation Steps Stage Installing the Screen Projector Place the PCM 340 on the T-bar Install Projector to Verify LocationMark Screen Location Mark the screen locationScrew the adjuster plate onto the base of the pipe Closest to the barrel on each arm, place Using the slots on the bracket that areViii. Evenly balanced configuration Verify the Image Location Slide and lock the projector onto the adjuster plateTake the measurements with the PCM 340 on the T-frame Preliminary Safety Hardware InstallationMark the structural ceiling for lag eye bolt installation Cut the Ceiling TileFinish Projector Drop Ceiling Mount Installation Hand tighten all four turnbuckles Secure the Projector Drop Ceiling Mount to the CeilingAttach the turnbuckles at the corners of the PCM Install the Screen Install the Electrical Box if requiredShock or serious injury. For safety Install the Raco box and plaster ring onto the PCMPage PVT CV D and PVT RGB D IP Plus AV Source Input Wallplates Cabling for the Wallplates and MediaLink Controller PVT transmitter installationMLC 104 IP Plus installation MLS 104 IP Plus MediaLink ControllerInsert the PVT mud ring into the wall Install the Mud RingsFeatures for MLC Mud Ring Installation Pull the cables at each location Signal Cable Label colorProvide strain relief Install Wall Plates Connect the MLC 104 IP Plus to the switcher Install MediaLink ControllerTerminal RS-232 Cable color Pin Connect to the LAN using a CAT 5 cableTCP/IP Connections made to the MLC 104 IP PlusCabling for the Speakers Stage 3 Involves Installing the Devices Shown BelowSpeaker Installation FF 120 Flat Field Ceiling SpeakersMark and cut the tile Install the Speaker on the Drop CeilingCut Ceiling Tile Attach safety cable Stereo output Dual mono output Terminate the Speaker Cable for the PVS SwitcherWire the captive screw connector Stereo or dual mono output using parallel speaker wiringRear View PVS 305SA IP PoleVault SwitcherStage 4 Involves Installing the Devices Shown Below PMK 550 Pole Mount KitInstall the PMK 550 Base Plate Gather the cables, pass them down the pipe Pull the Cables at the Switcher locationSwitcher and Projector Cable Overview Your completed connections should look like the image below Finish installing the Pole Mount KitConfigure the Switcher MLS Switcher Configuration Program Stage 5 Involves Installing the Programs Shown BelowConfigurator Configure the System GlobalTest the System Check that an image is present, and adjust as neededAdjust the audio levels on the PVS 305SA IP Test the MLC configuration is correctFinal Installation Preset Switch setting Resolution Number Using Preset ModeAny changes to the Edid settings as needed When the image is correct, re-install the wallplateOn the rear panel, set all the DIP switches to off down Using Learn Mode Available on PVT RGB D Plus onlyVoiceLift System Included parts Optional Accessory Installation VoiceLift SystemInstallation Procedure Priority Page Sensor Kit Included Parts Optional Accessory Installation Priority Page Sensor KitTypical paging system with PVS 305SA IP switcher Configuration program for MLSPoleVault Switchers PVS, available at Testing and Adjustment ProcedureExtron Warranty Outline of Installation Steps