MODEL NO.: |
|
| SERIAL NO.: |
|
| |
DATE: |
|
| TECHNICIAN: |
| ||
I. |
|
|
|
| ||
VERIFY THAT UNIT IS LEVEL |
|
|
|
|
VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
LOOSEN ALL SHIPPING HOLDDOWN BOLTS AND REMOVE SHIPPING BRACKETS PER INSTRUCTIONS
VERIFY THAT COMPRESSOR SUSPENSION SPRINGS HAVE BEEN LOOSENED PER INSTRUCTIONS
VERIFY OPENING OF ECONOMIZER HOODS
VERIFY INSTALLATION OF EXHAUST HOODS
CONFIRM THAT TUBING FOR SPACE AND SUPPLY DUCT PRESSURES HAS BEEN INSTALLED
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTRUCTIONS
VERIFY THAT POWER SUPPLY MATCHES UNIT DATA PLATE
VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT
CHECK GAS PIPING FOR LEAKS (48FK,JK ONLY)
CHECK THAT
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE, AND VERIFY SET SCREWS ARE TIGHT
VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED
OPEN SUCTION, DISCHARGE, AND LIQUID LINE SERVICE VALVES
CHECK COMPRESSOR OIL LEVEL SIGHT GLASS AND VERIFY PROPER LEVEL
VERIFY THAT CRANKCASE HEATERS HAVE BEEN ENERGIZED FOR 24 HOURS
CHECK VOLTAGE IMBALANCE
AB |
| V | AC |
|
| V | BC |
| V | |||||
(AB + AC + BC)/3 = AVERAGE VOLTAGE = |
|
|
|
| V |
|
|
|
|
| ||||
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE = |
|
|
| V |
|
| ||||||||
VOLTAGE IMBALANCE = 100 X (MAX DEVIATION)/(AVERAGE VOLTAGE) = |
|
| % |
IF OVER 2% VOLTAGE IMBALANCE, DO NOT ATTEMPT TO START SYSTEM!
CALL LOCAL POWER COMPANY FOR ASSISTANCE.
II. PRELIMINARY CHECKLIST ITEMS:
CONTROL SETTINGS
DIP SWITCHES SET TO MATCH INSTALLED ACCESSORIES:
SUPPLY AIR SET POINT RESET (DIP SWITCH NO. 4 ON)
MORNING
DEMAND LIMIT (DIP SWITCH NO. 5 ON)
SUPPLY AIR SET POINT (P1) SET BETWEEN 45 AND 70 F
ECONOMIZER MINIMUM POSITION (P5) SET PER PLANS
SUPPLY AIR SET POINT RESET SETTINGS:
RESET INITIATION TEMPERATURE (P7) (TYPICALLY 68 TO 72 F)
RESET LIMIT TEMPERATURE (P3) (TYPICALLY 60 TO 70 F)
MORNING
IGV/VFD DUCT PRESSURE SET POINT PER PLANS
BUILDING PRESSURE (MODULATING POWER EXHAUST) SET PER PLANS
DEMAND LIMIT SETTINGS PER PLAN:
SINGLE STEP DEMAND LIMIT (P4) SET (TYPICALLY 25 TO 50%)
OCCUPIED/UNOCCUPIED SWITCH INSTALLED PER FIG. 21 (CLOSE TO START UNIT)