Page 92 of 332 Chapter 6 — Installing the Option 11C Mini

Readiness checklist

Have you:

read all safety instructions in “Chapter 7 — Important safety instructions” on page 101?

made sure that you received all the equipment that you ordered?

made sure your area meets all environmental requirements?

checked for all power requirements?

checked for correct grounding facilities?

developed an equipment layout plan for the system? See “Equipment layout plan” on page 69.

completed the card slot assignment plan? See “Card slot assignments” on page 77.

assembled all the tools required to continue with the installation?

If you have completed all of the above items, you are ready to start the installation of the Option 11C Mini system.

Summary of installation procedures

The following list provides a summary of the Option 11C Mini installation procedures. Refer to the chapters and procedures indicated at the end of each step for important and detailed information related to installation.

1Read the safety instructions in “Chapter 7 — Important safety instructions” on page 101.

2Make sure that you have read and completed the instructions contained in the Planning section of this guide.

3Make sure that system and site requirements have been met. See “Chapter 3 — System and site requirements” on page 45.

4Make sure that you have created the equipment layout plan and card slot assignment plan. See “Chapter 4 — Creating an equipment layout plan and a card slot assignment plan” on page 69.