Page 210 of 332 Chapter 16 — Starting the Option 11C Mini and insta lling software

Start-up procedures

Procedure 27

Start-up procedure for a new system installation, using the MSC card

1Test the power outlet. Make sure that the correct voltage of power is present before you plug the power cord into the outlet. The source must match the label on the back of the chassis.

2Connect the power cord from the power connector on the back of the chassis to an AC power source. See Figure 63. Secure the power cable with a cable tie.

Figure 63

Power connector on the back of the chassis

Power cord

Cable tie

3Turn the power switch to “ON”.

4Observe the TTY or terminal screen. The TTY must be connected to TTY port 0.

5When you have completed the software installation (see “Installing software in a new system” on page 215), observe the screen again.

553-3021-209 Standard 3.00 April 2000

Page 210
Image 210
Nortel Networks Option 11C Mini manual Start-up procedures, Power connector on the back of the chassis