State Industries SUF-60-120, SUF-100-250 Water Damage Hazard, Temperature-Pressure Relief Valve

Page 16

Temperature-Pressure Relief Valve

Explosion Hazard

Temperature-Pressure Relief Valve must comply with ANSI Z21.22- CSA 4.4 and ASME code.

Properly sized temperature- pressure relief valve must be installed in opening provided.

Can result in overheating and excessive tank pressure.

Can cause serious injury or death.

This water heater is provided with a properly rated/sized and certified combination Temperature-Pressure Relief Valve (T&P valve) by the manufacturer. The valve is certified by a nationally recognized testing laboratory that maintains periodic inspection of production of listed equipment of materials as meeting the requirements for Relief Valves for Hot Water Supply Systems, ANSI Z21.22 • CSA 4.4, and the code requirements of ASME.

If replaced, the new T&P valve must meet the requirements of local codes, but not less than a combination Temperature- Pressure Relief Valve rated/sized and certified as indicated in the above paragraph. The new valve must be marked with a maximum set pressure not to exceed the marked hydrostatic working pressure of the water heater (150 psi = 1,035 kPa) and a discharge capacity not less than the water heater Btu/hr or kW input rate as shown on the water heater’s model rating label.

Note: In addition to the factory installed Temperature-Pressure Relief Valve on the water heater, each remote storage tank that may be installed and piped to a water heating appliance must also have its own properly sized, rated and approved Temperature- Pressure Relief Valve installed. Call the toll free technical support phone number listed on the back cover of this manual for technical assistance in sizing a Temperature-Pressure Relief Valve for remote storage tanks.

For safe operation of the water heater, the Temperature-Pressure Relief Valve must not be removed from its designated opening nor plugged. The Temperature-Pressure Relief Valve must be installed directly into the fitting of the water heater designed for the relief valve. Install discharge piping so that any discharge will exit the pipe within 6 inches (15.2 cm) above an adequate floor drain, or external to the building. In cold climates it is recommended that it be terminated at an adequate drain inside the building. Be certain that no contact is made with any live electrical part. The discharge opening must not be blocked or reduced in size under any circumstances. Excessive length, over 30 feet (9.14 m), or use of more than four elbows can cause restriction and reduce the discharge capacity of the valve.

No valve or other obstruction is to be placed between the Temperature-Pressure Relief Valve and the tank. Do not connect discharge piping directly to the drain unless a 6” (15.2 cm) air gap is provided. To prevent bodily injury, hazard to life, or property damage, the relief valve must be allowed to discharge water in adequate quantities should circumstances demand. If the discharge pipe is not connected to a drain or other suitable means, the water flow may cause property damage.

CAUTION

Water Damage Hazard

Temperature-Pressure Relief Valve discharge pipe must terminate at adequate drain.

T&P Valve Discharge Pipe Requirements:

Shall not be smaller in size than the outlet pipe size of the valve, or have any reducing couplings or other restrictions.

Shall not be plugged or blocked.

Shall not be exposed to freezing temperatures.

Shall be of material listed for hot water distribution.

Shall be installed so as to allow complete drainage of both the Temperature-Pressure Relief Valve and the discharge pipe.

Must terminate a maximum of six inches above a floor drain or external to the building. In cold climates, it is recommended that the discharge pipe be terminated at an adequate drain inside the building.

Shall not have any valve or other obstruction between the relief valve and the drain.

Burn hazard.

Hot water discharge.

Keep clear of Temperature- Pressure Relief Valve discharge outlet.

The Temperature-Pressure Relief Valve must be manually operated at least twice a year. Caution should be taken to ensure that (1) no one is in front of or around the outlet of the Temperature-Pressure Relief Valve discharge line, and (2) the water manually discharged will not cause any bodily injury or property damage because the water may be extremely hot. If after manually operating the valve, it fails to completely reset and continues to release water, immediately close the cold water inlet to the water heater, follow the draining instructions in this manual, and replace the Temperature-Pressure Relief Valve with a properly rated/sized new one.

Note: The purpose of a Temperature-Pressure Relief Valve is to prevent excessive temperatures and pressures in the storage tank. The T&P valve is not intended for the constant relief of thermal expansion. A properly sized thermal expansion tank must be installed on all closed systems to control thermal expansion, see Closed Water Systems and Thermal Expansion on page 15.

If you do not understand these instructions or have any questions regarding the Temperature-Pressure Relief Valve call the toll free number listed on the back cover of this manual for technical assistance.

16

Image 16
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ApprovalsGeneral Safety Information PrecautionsHydrogen Gas Flammable Overheated water can cause water tank explosionFire or Explosion Hazard Installing, using or servicing Water heaterFire and Explosion Hazard Preparing For The Installation IntroductionAbbreviations Used QualificationsFeatures And Components Basic OperationTop Views 120,000 & 150,000 Water Heater’s 120 VAC on/off switchSUF 120 & 150 Components SUF 199 & 250 Components Top ViewsWater heaters 24 Volt Gas Valve Left Side Right Side Rough In Dimensions Installation ConsiderationsTOP Views Recovery Capacities Locating The Water HeaterGas Line Connection Size Storage CapacitiesExtended Vent Terminations Optional Concentric TerminationsHard Water Circulation PumpsInstallation Requirements Power SupplyGas Pressure Requirements Supply Gas LineMixing Valves Dishwashing MachinesClosed Water Systems Thermal ExpansionWater Damage Hazard Temperature-Pressure Relief ValveValve Discharge Pipe Requirements Condensate Drain Combustible Material StorageContaminated Air Condensate Drain Water TrapBreathing Hazard Carbon Monoxide Gas Air RequirementsUnconfined Space Confined SpaceFresh Air Openings For Confined Spaces Outdoor Air Through Two OpeningsOutdoor Air Through One Opening Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionGeneral Venting Information Venting InstallationGeneral Venting Instructions SUF 199 & SUF 250 Intake Air Connection Correct OrientationLarge Hose Fernco Clamp TEE FittingVenting Requirements Power Vent Installation Venting Installation SequenceDirect Vent Installation Intake AIR Screen Field SuppliedVertical Termination Installation Standard Factory Supplied TerminationsField Supplied STRAP/SUPPORT Maximum Factory Supplied Standard TerminationIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Concentric Termination Installation Determine the location for the terminationInch Concentric Termination Installation Inch Concentric Termination KITTWO Concentric Terminations Three Concentric TerminationsFour Concentric Terminations Eight Concentric TerminationsMultiple Concentric Termination Arrangements Two Concentric TerminationsEight Concentric Terminations Sidewall RoofVenting Arrangements Power Vent HorizontalDirect Vent Horizontal Direct Vent Horizontal Vent Vertical Intake Direct Vent Vertical Vent Horizontal IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentWater Heater Installation Condensate Drain InstallationInstallation Notes Installation InstructionsSupply Gas Line Installation Gas Line SizingSupply Gas Line Sizing U. S. Units Supply Gas Line Sizing Metric UnitsGas Line Leak Testing Supply Gas Regulator InstallationGas Line Connection Electrical Wiring Power Supply ConnectionsEnable/Disable Circuit Connecting An External Supervisory ControlWater Piping Diagrams Water Line ConnectionsValve Discharge Pipe Thermometers not SuppliedTemperature Regulation High Temperature Limit Control ECOHigh Temperature Applications Thermostat ControlTank Temperature 103F Operating Set Point 120F Control System OperationOverview Control System NavigationStatus Icons Icon DescriptionOperating States State DescriptionControl System Menus Menu DescriptionUser Settings & Control System Menus Update CancelBack Help Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayBack Advanced View Back HelpECO YESUpdate Service Contact InformationSelect Back Help NamePrior to Start up Start UpInitial Start Up GAS Valve / Venturi Assembly TOP View GAS Valve TOP Detail ViewLighting The Water Heater Gas pressure reading while the water heater is firingMultiple Appliance Installations High Altitude Installations Checking The Firing Rate1050 = 300,000 Btu/hr 87.9 kW To Turn Off GasSUF 60 120 and SUF 100 150 Models only Lighting The Water HeaterLighting & Operation Labels Tank Temperature 103F Operating Set Point 120F SUF 100 199 and SUF 100 250 Models onlyInstallation Checklist TroubleshootingSequence Of Operation Closed by control system Fault Msg is displayed Sequence Of Operation Flow ChartPre-Purge cycle Operational Problems Installation ErrorsRough Starting, Rough Operation Momentary IgnitionFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesBack Advanced Blower Prover Failure No Anode VoltageMaintenance Maintenance ScheduleGeneral Draining And FlushingFilling The Water Heater Sediment RemovalLime Scale Removal Manual Lime Scale RemovalPowered Anode Rods Drain Valve and Access PanelsTemperature-Pressure Relief Valve Test Vent SystemDiagrams J3 J5J10 J13 J11 CCB Central Control Board LayoutSUF 120 & 150 Wiring Diagram User Interface ModulSUF 199 & 250 Wiring Diagram CCB Central Control BoardCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty