Air Requirements

Breathing Hazard - Carbon Monoxide Gas

Install water heater in accordance with the Instruction Manual and NFPA 54 or CAN/CSA-B149.1.

To avoid injury, combustion and ventilation air must be taken from outdoors.

Do not place chemical vapor emitting products near water heater.

Breathing carbon monoxide can cause brain damage or death. Always read and understand instruction manual.

For safe operation an adequate supply of fresh uncontaminated air for combustion and ventilation must be provided.

An insufficient supply of air can cause recirculation of combustion products resulting in contamination that may be hazardous to life. Such a condition often will result in a yellow, luminous burner flame, causing sooting of the combustion chamber, burners and flue tubes and creates a risk of asphyxiation.

Do not install the water heater in a confined space unless an adequate supply of air for combustion and ventilation is brought in to that space using the methods described in the Confined Space section that follows.

Never obstruct the flow of ventilation air. If you have any doubts or questions at all, call your gas supplier. Failure to provide the proper amount of combustion air can result in a fire or explosion and cause property damage, serious bodily injury or death.

Unconfined Space

An Unconfined Space is one whose volume is not less than 50 cubic feet per 1,000 Btu/hr (4.8 cubic meters per kW) of the total input rating of all appliances installed in the space. Rooms communicating directly with the space, in which the appliances are installed, through openings not furnished with doors, are considered a part of the unconfined space.

Makeup air requirements for the operation of exhaust fans, kitchen ventilation systems, clothes dryers and fireplaces shall also be considered in determining the adequacy of a space to provide combustion, ventilation and dilution air.

Unusually Tight Construction

In unconfined spaces in buildings, infiltration may be adequate to provide air for combustion, ventilation and dilution of flue gases. However, in buildings of unusually tight construction (for example, weather stripping, heavily insulated, caulked, vapor barrier, etc.) additional air must be provided using the methods described in the Confined Space section that follows.

Confined Space

A Confined Space is one whose volume is less than 50 cubic feet per 1,000 Btu/hr (4.8 cm per kW) of the total input rating of all appliances installed in the space.

Openings must be installed to provide fresh air for combustion, ventilation and dilution in confined spaces. The required size for the openings is dependent on the method used to provide fresh air to the confined space and the total Btu/hr input rating of all appliances installed in the space.

Direct Vent Appliances

Appliances installed in a Direct Vent configuration that derive all air for combustion from the outdoor atmosphere through sealed intake air piping are not factored in the total appliance input Btu/ hr calculations used to determine the size of openings providing fresh air into confined spaces.

Exhaust Fans

Where exhaust fans are installed, additional air shall be provided to replace the exhausted air. When an exhaust fan is installed in the same space with a water heater, sufficient openings to provide fresh air must be provided that accommodate the requirements for all appliances in the room and the exhaust fan. Undersized openings will cause air to be drawn into the room through the water heater’s vent system causing poor combustion. Sooting, serious damage to the water heater and the risk of fire or explosion may result. It can also create a risk of asphyxiation.

Louvers and Grilles

The free areas of the fresh air openings in the instructions that follow do not take in to account the presence of louvers, grilles or screens in the openings.

The required size of openings for combustion, ventilation and dilution air shall be based on the “net free area” of each opening. Where the free area through a design of louver or grille or screen is known, it shall be used in calculating the size of opening required to provide the free area specified. Where the louver and grille design and free area are not known, it shall be assumed that wood louvers will have 25% free area and metal louvers and grilles will have 75% free area. Non motorized louvers and grilles shall be fixed in the open position.

18

Image 18
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ApprovalsHydrogen Gas Flammable General Safety InformationPrecautions Overheated water can cause water tank explosionInstalling, using or servicing Water heater Fire or Explosion HazardFire and Explosion Hazard Abbreviations Used Preparing For The InstallationIntroduction QualificationsFeatures And Components Basic OperationWater Heater’s 120 VAC on/off switch Top Views 120,000 & 150,000SUF 120 & 150 Components Top Views SUF 199 & 250 ComponentsWater heaters 24 Volt Gas Valve Left Side Right Side Installation Considerations Rough In DimensionsTOP Views Gas Line Connection Size Recovery CapacitiesLocating The Water Heater Storage CapacitiesHard Water Extended Vent TerminationsOptional Concentric Terminations Circulation PumpsGas Pressure Requirements Installation RequirementsPower Supply Supply Gas LineClosed Water Systems Mixing ValvesDishwashing Machines Thermal ExpansionTemperature-Pressure Relief Valve Water Damage HazardValve Discharge Pipe Requirements Contaminated Air Condensate DrainCombustible Material Storage Condensate Drain Water TrapUnconfined Space Breathing Hazard Carbon Monoxide GasAir Requirements Confined SpaceOutdoor Air Through One Opening Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionVenting Installation General Venting InformationGeneral Venting Instructions Large Hose Fernco Clamp SUF 199 & SUF 250 Intake Air ConnectionCorrect Orientation TEE FittingVenting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation Intake AIR Screen Field SuppliedVertical Termination Installation Standard Factory Supplied TerminationsMaximum Factory Supplied Standard Termination Field Supplied STRAP/SUPPORTIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Concentric Termination Installation Determine the location for the terminationInch Concentric Termination Installation Inch Concentric Termination KITFour Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Eight Concentric TerminationsEight Concentric Terminations Multiple Concentric Termination ArrangementsTwo Concentric Terminations Sidewall RoofPower Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentInstallation Notes Water Heater InstallationCondensate Drain Installation Installation InstructionsSupply Gas Line Sizing U. S. Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing Metric UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Enable/Disable Circuit Electrical WiringPower Supply Connections Connecting An External Supervisory ControlValve Discharge Pipe Water Piping DiagramsWater Line Connections Thermometers not SuppliedHigh Temperature Applications Temperature RegulationHigh Temperature Limit Control ECO Thermostat ControlOverview Tank Temperature 103F Operating Set Point 120FControl System Operation Control System NavigationStatus Icons Icon DescriptionControl System Menus Operating StatesState Description Menu DescriptionBack Help User Settings & Control System MenusUpdate Cancel Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayECO Back AdvancedView Back Help YESSelect Back Help UpdateService Contact Information NameStart Up Prior to Start upInitial Start Up Lighting The Water Heater GAS Valve / Venturi Assembly TOP ViewGAS Valve TOP Detail View Gas pressure reading while the water heater is firingMultiple Appliance Installations 1050 = 300,000 Btu/hr 87.9 kW High Altitude InstallationsChecking The Firing Rate To Turn Off GasLighting The Water Heater SUF 60 120 and SUF 100 150 Models onlyLighting & Operation Labels Tank Temperature 103F Operating Set Point 120F SUF 100 199 and SUF 100 250 Models onlyTroubleshooting Installation ChecklistSequence Of Operation Sequence Of Operation Flow Chart Closed by control system Fault Msg is displayedPre-Purge cycle Rough Starting, Rough Operation Operational ProblemsInstallation Errors Momentary IgnitionFault And Alert Conditions Fault And Alert Messages Possible Causes Check/Repair Displayed Fault/Alert MessageBack Advanced Blower Prover Failure No Anode VoltageGeneral MaintenanceMaintenance Schedule Draining And FlushingLime Scale Removal Filling The Water HeaterSediment Removal Manual Lime Scale RemovalTemperature-Pressure Relief Valve Test Powered Anode RodsDrain Valve and Access Panels Vent SystemJ10 J13 J11 DiagramsJ3 J5 CCB Central Control Board LayoutSUF 120 & 150 Wiring Diagram User Interface ModulSUF 199 & 250 Wiring Diagram CCB Central Control BoardCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty