Water Line Connections

The water piping installation must conform to these instructions and to all local and national code authority having jurisdiction. Good practice requires that all heavy piping be supported.

Read and observe all requirements in the following sections before installation of the water piping begins:

1.Mixing Valves on page 15.

2.Dishwashing Machines on page 15.

3.Temperature-Pressure Relief Valve on page 16.

4.Closed Systems and Thermal Expansion on page 15.

5.For multiple water heater installations see Water Piping

Diagrams beginning on page 71.

Water Piping Diagrams

This manual provides detailed water piping diagrams for typical methods of application for the water heaters, see Water Piping Diagrams beginning 71.

The water heater may be installed by itself, or with a separate storage tank. When used with a separate storage tank, the circulation may be either by gravity or by means of circulating pump. When a circulating pump is used, it is important to note that the flow rate should be slow so that there will be a minimum of turbulence inside the water heater storage tank.

Adjust flow by throttling a full port ball valve installed in the circulating line on the outlet side of the pump. Never throttle flow on the suction side of a pump. See the Water Piping Diagrams beginning on page 71.

Note: In addition to the factory installed Temperature-Pressure Relief Valve (T&P valve) on the water heater, each remote storage tank that may be installed and piped to a water heating appliance must also have its own properly sized, rated and approved Temperature-Pressure Relief Valve installed.

Call the toll free technical support phone number listed on the back cover of this manual for further assistance in sizing a T&P valve for remote storage tanks.

Thermometers (not Supplied)

Thermometers are installed in the water piping system as a means of detecting the temperature of the hot water supply at critical points in the system. Field supplied thermometers should be obtained and installed. See Water Piping Diagrams on page 71.

Water (potable) Heating And Space Heating

1.All water piping components connected to the water heater that are for space heating applications shall be suitable for use with potable water.

2.Toxic chemicals, such as those used for boiler treatment, must NEVER be introduced into this system.

3.The water heaters covered in this manual may never be connected to any existing heating system or component(s) previously used with non-potable water heating appliance.

4.When the system requires water for space heating that exceed safe temperatures at domestic water fixtures a mixing valve must be installed, see Mixing Valves on page 15.

T&P Valve Discharge Pipe

Explosion Hazard

Temperature-Pressure Relief Valve must comply with ANSI Z21.22- CSA 4.4 and ASME code.

Properly sized temperature- pressure relief valve must be installed in opening provided.

Can result in overheating and excessive tank pressure.

Can cause serious injury or death.

This water heater is provided with a properly rated/sized and certified combination temperature - pressure (T&P) relief valve by the manufacturer. See Temperature-Pressure Relief Valve on page 16 for information on replacement and other requirements.

CAUTION

Water Damage Hazard

Temperature-Pressure Relief Valve discharge pipe must terminate at adequate drain.

Install a discharge pipe between the T&P valve discharge opening and a suitable floor drain. Do not connect discharge piping directly to the drain unless a 6” (15.2 cm) air gap is provided. To prevent bodily injury, hazard to life, or property damage, the relief valve must be allowed to discharge water in adequate quantities should circumstances demand. If the discharge pipe is not connected to a drain or other suitable means, the water flow may cause property damage.

T&P Valve Discharge Pipe Requirements:

Shall not be smaller in size than the outlet pipe size of the valve, or have any reducing couplings or other restrictions.

Shall not be plugged or blocked.

Shall not be exposed to freezing temperatures.

Shall be of material listed for hot water distribution.

Shall be installed so as to allow complete drainage of both the Temperature-Pressure Relief Valve and the discharge pipe.

Must terminate a maximum of six inches above a floor drain or external to the building. In cold climates, it is recommended that the discharge pipe be terminated at an adequate drain inside the building.

Shall not have any valve or other obstruction between the relief valve and the drain.

42

Image 42
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ApprovalsHydrogen Gas Flammable General Safety InformationPrecautions Overheated water can cause water tank explosionInstalling, using or servicing Water heater Fire or Explosion HazardFire and Explosion Hazard Abbreviations Used Preparing For The InstallationIntroduction QualificationsFeatures And Components Basic OperationWater Heater’s 120 VAC on/off switch Top Views 120,000 & 150,000SUF 120 & 150 Components Top Views SUF 199 & 250 ComponentsWater heaters 24 Volt Gas Valve Left Side Right Side Installation Considerations Rough In DimensionsTOP Views Gas Line Connection Size Recovery CapacitiesLocating The Water Heater Storage CapacitiesHard Water Extended Vent TerminationsOptional Concentric Terminations Circulation PumpsGas Pressure Requirements Installation RequirementsPower Supply Supply Gas LineClosed Water Systems Mixing ValvesDishwashing Machines Thermal ExpansionTemperature-Pressure Relief Valve Water Damage HazardValve Discharge Pipe Requirements Contaminated Air Condensate DrainCombustible Material Storage Condensate Drain Water TrapUnconfined Space Breathing Hazard Carbon Monoxide GasAir Requirements Confined SpaceOutdoor Air Through One Opening Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionVenting Installation General Venting InformationGeneral Venting Instructions Large Hose Fernco Clamp SUF 199 & SUF 250 Intake Air ConnectionCorrect Orientation TEE FittingVenting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation Intake AIR Screen Field SuppliedVertical Termination Installation Standard Factory Supplied TerminationsMaximum Factory Supplied Standard Termination Field Supplied STRAP/SUPPORTIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Concentric Termination Installation Determine the location for the terminationInch Concentric Termination Installation Inch Concentric Termination KITFour Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Eight Concentric TerminationsEight Concentric Terminations Multiple Concentric Termination ArrangementsTwo Concentric Terminations Sidewall RoofPower Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentInstallation Notes Water Heater InstallationCondensate Drain Installation Installation InstructionsSupply Gas Line Sizing U. S. Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing Metric UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Enable/Disable Circuit Electrical WiringPower Supply Connections Connecting An External Supervisory ControlValve Discharge Pipe Water Piping DiagramsWater Line Connections Thermometers not SuppliedHigh Temperature Applications Temperature RegulationHigh Temperature Limit Control ECO Thermostat ControlOverview Tank Temperature 103F Operating Set Point 120FControl System Operation Control System NavigationStatus Icons Icon DescriptionControl System Menus Operating StatesState Description Menu DescriptionBack Help User Settings & Control System MenusUpdate Cancel Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayECO Back AdvancedView Back Help YESSelect Back Help UpdateService Contact Information NameStart Up Prior to Start upInitial Start Up Lighting The Water Heater GAS Valve / Venturi Assembly TOP ViewGAS Valve TOP Detail View Gas pressure reading while the water heater is firingMultiple Appliance Installations 1050 = 300,000 Btu/hr 87.9 kW High Altitude InstallationsChecking The Firing Rate To Turn Off GasLighting The Water Heater SUF 60 120 and SUF 100 150 Models onlyLighting & Operation Labels Tank Temperature 103F Operating Set Point 120F SUF 100 199 and SUF 100 250 Models onlyTroubleshooting Installation ChecklistSequence Of Operation Sequence Of Operation Flow Chart Closed by control system Fault Msg is displayedPre-Purge cycle Rough Starting, Rough Operation Operational ProblemsInstallation Errors Momentary IgnitionFault And Alert Conditions Fault And Alert Messages Possible Causes Check/Repair Displayed Fault/Alert MessageBack Advanced Blower Prover Failure No Anode VoltageGeneral MaintenanceMaintenance Schedule Draining And FlushingLime Scale Removal Filling The Water HeaterSediment Removal Manual Lime Scale RemovalTemperature-Pressure Relief Valve Test Powered Anode RodsDrain Valve and Access Panels Vent SystemJ10 J13 J11 DiagramsJ3 J5 CCB Central Control Board LayoutSUF 120 & 150 Wiring Diagram User Interface ModulSUF 199 & 250 Wiring Diagram CCB Central Control BoardCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty