State Industries SUF-60-120, SUF-100-250 instruction manual Prior to Start up, Initial Start Up

Page 52

Start Up

Prior to Start up

Installation and start up of this water heater requires abilities and skills equivalent to that of a licensed tradesman in the field involved, see Qualifications on page 6.

Do not place the water heater in operation if any part has been under water. Immediately call a qualified service technician to inspect the water heater and to replace any part of the control system and any gas control which has been under water.

Light the water heater in accordance with the Lighting and Operation Instruction label on the water heater and in this manual beginning on page 56.

The water heaters covered by this manual are equipped with an electronic control system (see page 44) which automatically sequences the Combustion Blower, pre and post purging of the combustion chamber, the Hot Surface Igniter, the 24 Volt Gas Valve, Main Burner ignition, and flame sensing. The control system will lock out after three unsuccessful ignition attempts.

Before attempting start up, thoroughly study and familiarize yourself with the exact Sequence Of Operation, see the written Sequence Of Operation on page 58 and the Sequence Of Operation Flow Chart on page 59.

Be certain that the water heater is full of water, that air is purged from the gas and water lines and that there are no leaks in the gas and water lines. Ensure all inlet water valves are open.

Filling The Water Heater

Follow these steps to fill the water heater prior to start up.

1.Close the heater drain valve.

2.Open a nearby hot water faucet to permit the air in the system to escape.

3.Fully open the cold water inlet valve allowing the piping and water heater to fill with water.

4.Close the hot water faucet opened in Step 2 as water starts to flow.

Supply Gas Line Purging

Fire or Explosion Hazard

Gas line purging is required with new piping or systems in which air has entered.

To avoid risk of fire or explosion purge discharge must not enter into confined areas or spaces where ignition can occur.

The area must be well ventilated and all sources of ignition must be deactivated or removed.

Use only the gas shown on the water heater rating label.

Keep ignition sources away from faucets after extended periods of non-use.

Read instruction manual before

installing, using or servicing

water heater.

1.Close the Main Gas Shutoff Valve, see Figure 52 on page 39.

2.Purge all air from the supply gas line up to the water heater’s

Main Gas Shutoff Valve.

3.When all air has been purged from the supply gas line, tighten all supply gas line connections.

4.Check for gas leaks, see Gas Line Leak Testing on page 40, and repair any leaks found.

Initial Start Up

Required Test Equipment

Two U-tube manometers, recommended ranges; 0-14” W.C. (0-3.5 kPa) and 0-35” W.C. (0-8.7 kPa) or pressure gauges.

Two digital manometers can be used in place of U-tube manometers or pressure gauges. Recommended ranges; -14.00 to +14.00” W.C. (0-3.5 kPa) resolution 0.01” W.C. and 0-35” W.C. (0-8.7 kPa) resolution 0.10” W.C.

Note: All test equipment must be acclimated to ambient temperature before calibration and use.

Preparation

1.Using the control system menus, change the Operating Set Point to the lowest temperature setting, see Operating Set Point And Differential Adjustment on page 47.

2.Turn the water heater’s on/off switch to the “off” position.

3.Close the Main Gas Shut Off Valve, see Figure 52 on page 39.

4.Wait five (5) minutes for any residual gas to clear.

5.Connect one manometer (higher range) to an available test port for the supply gas pressure to the water heater:

On SUF 120 and 150 models there is a 1/8" NPT Tee fitting and pipe nipple installed for the Low Gas Pressure switch on the inlet side of the 24 Volt Gas Valve with a 1/8" pipe plug for this purpose. Remove the 1/8 inch pipe plug from the bottom of the Tee fitting and install a barb fitting to connect the manometer sensing tube, see Figure 58 on page 53.

On SUF 199 and 250 models there are test ports for supply and manifold gas pressure readings on the gas valve. Using a small flat tip pocket screw driver - open the needle valve inside the supply gas pressure test port one full turn only; turn the needle valve screw counter-clockwise to open the valve. Slide the manometer sensing tube over the top of the test port, see Figure 59 and Figure 60 on page 53.

6.Connect one manometer (lower range) to an available test port for manifold gas pressure to the Main Burner:

SUF 120 & 150 models: remove the 1/8 inch pipe plug from the body of the gas valve on the outlet side and install a barb fitting to connect the manometer sensing tube, see Figure 57 on page 53.

SUF 199 & 250 models: Using a small flat tip pocket screw driver - open the needle valve inside the manifold gas pressure test port one full turn only; turn the needle valve screw counter-clockwise to open the valve. Slide the manometer sensing tube over the top of the test port, see Figure 59 and Figure 60 on page 53.

7.Open the Main Gas Shutoff Valve.

8.Measure and record the supply gas pressure, this is a “static” supply gas pressure reading; while the water heater is not firing. Adjust supply gas pressure as necessary, see Supply Gas Pressure Adjustment on page 54.

52

Image 52
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ApprovalsGeneral Safety Information PrecautionsHydrogen Gas Flammable Overheated water can cause water tank explosionFire or Explosion Hazard Installing, using or servicing Water heaterFire and Explosion Hazard Preparing For The Installation IntroductionAbbreviations Used QualificationsFeatures And Components Basic OperationTop Views 120,000 & 150,000 Water Heater’s 120 VAC on/off switchSUF 120 & 150 Components SUF 199 & 250 Components Top ViewsWater heaters 24 Volt Gas Valve Left Side Right Side Rough In Dimensions Installation ConsiderationsTOP Views Recovery Capacities Locating The Water HeaterGas Line Connection Size Storage CapacitiesExtended Vent Terminations Optional Concentric TerminationsHard Water Circulation PumpsInstallation Requirements Power SupplyGas Pressure Requirements Supply Gas LineMixing Valves Dishwashing MachinesClosed Water Systems Thermal ExpansionWater Damage Hazard Temperature-Pressure Relief ValveValve Discharge Pipe Requirements Condensate Drain Combustible Material StorageContaminated Air Condensate Drain Water TrapBreathing Hazard Carbon Monoxide Gas Air RequirementsUnconfined Space Confined SpaceFresh Air Openings For Confined Spaces Outdoor Air Through Two OpeningsOutdoor Air Through One Opening Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionGeneral Venting Information Venting InstallationGeneral Venting Instructions SUF 199 & SUF 250 Intake Air Connection Correct OrientationLarge Hose Fernco Clamp TEE FittingVenting Requirements Power Vent Installation Venting Installation SequenceDirect Vent Installation Intake AIR Screen Field SuppliedVertical Termination Installation Standard Factory Supplied TerminationsField Supplied STRAP/SUPPORT Maximum Factory Supplied Standard TerminationIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Concentric Termination Installation Determine the location for the terminationInch Concentric Termination Installation Inch Concentric Termination KITTWO Concentric Terminations Three Concentric TerminationsFour Concentric Terminations Eight Concentric TerminationsMultiple Concentric Termination Arrangements Two Concentric TerminationsEight Concentric Terminations Sidewall RoofVenting Arrangements Power Vent HorizontalDirect Vent Horizontal Direct Vent Horizontal Vent Vertical Intake Direct Vent Vertical Vent Horizontal IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentWater Heater Installation Condensate Drain InstallationInstallation Notes Installation InstructionsSupply Gas Line Installation Gas Line SizingSupply Gas Line Sizing U. S. Units Supply Gas Line Sizing Metric UnitsGas Line Leak Testing Supply Gas Regulator InstallationGas Line Connection Electrical Wiring Power Supply ConnectionsEnable/Disable Circuit Connecting An External Supervisory ControlWater Piping Diagrams Water Line ConnectionsValve Discharge Pipe Thermometers not SuppliedTemperature Regulation High Temperature Limit Control ECOHigh Temperature Applications Thermostat ControlTank Temperature 103F Operating Set Point 120F Control System OperationOverview Control System NavigationStatus Icons Icon DescriptionOperating States State DescriptionControl System Menus Menu DescriptionUser Settings & Control System Menus Update CancelBack Help Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayBack Advanced View Back HelpECO YESUpdate Service Contact InformationSelect Back Help NamePrior to Start up Start UpInitial Start Up GAS Valve / Venturi Assembly TOP View GAS Valve TOP Detail ViewLighting The Water Heater Gas pressure reading while the water heater is firingMultiple Appliance Installations High Altitude Installations Checking The Firing Rate1050 = 300,000 Btu/hr 87.9 kW To Turn Off GasSUF 60 120 and SUF 100 150 Models only Lighting The Water HeaterLighting & Operation Labels Tank Temperature 103F Operating Set Point 120F SUF 100 199 and SUF 100 250 Models onlyInstallation Checklist TroubleshootingSequence Of Operation Closed by control system Fault Msg is displayed Sequence Of Operation Flow ChartPre-Purge cycle Operational Problems Installation ErrorsRough Starting, Rough Operation Momentary IgnitionFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesBack Advanced Blower Prover Failure No Anode VoltageMaintenance Maintenance ScheduleGeneral Draining And FlushingFilling The Water Heater Sediment RemovalLime Scale Removal Manual Lime Scale RemovalPowered Anode Rods Drain Valve and Access PanelsTemperature-Pressure Relief Valve Test Vent SystemDiagrams J3 J5J10 J13 J11 CCB Central Control Board LayoutSUF 120 & 150 Wiring Diagram User Interface ModulSUF 199 & 250 Wiring Diagram CCB Central Control BoardCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty