State Industries SUF-100-250, SUF-60-120 instruction manual Fresh Air Openings For Confined Spaces

Page 19

Fresh Air Openings For Confined Spaces

The following instructions shall be used to calculate the size, number and placement of openings providing fresh air for combustion, ventilation and dilution in confined spaces. The illustrations shown in this section of the manual are a reference for the openings that provide fresh air into confined spaces only. Do not refer to these illustrations for the purpose of vent installation. See Venting Installation on page 22 for complete venting installation instructions.

Outdoor Air Through Two Openings

Figure 10

The confined space shall be provided with two permanent openings, one commencing within 12 inches (300 mm) of the top and one commencing within 12 inches (300 mm) of the bottom of the enclosure. The openings shall communicate directly with the outdoors. See Figure 10.

Each opening shall have a minimum free area of 1 square inch per 4,000 Btu/hr (550 mm2 per kW) of the aggregate input rating of all appliances installed in the enclosure. Each opening shall not be less than 100 square inches (645 cm2).

Outdoor Air Through One Opening

Figure 11

Alternatively a single permanent opening, commencing within 12 inches (300 mm) of the top of the enclosure, shall be provided. See Figure 11. The water heater shall have clearances of at least 1 inch (25 mm) from the sides and back and 6 inches (l50

mm)from the front of the appliance. The opening shall directly communicate with the outdoors or shall communicate through a vertical or horizontal duct to the outdoors or spaces that freely communicate with the outdoors and shall have a minimum free area of the following:

1.1 square inch per 3000 Btu/hr (700 mm2 per kW) of the total input rating of all appliances located in the enclosure, and

2.Not less than the sum of the areas of all vent connectors in the space.

Outdoor Air Through Two Horizontal Ducts

Figure 12

The confined space shall be provided with two permanent horizontal ducts, one commencing within 12 inches (300 mm) of the top and one commencing within 12 inches (300 mm) of the bottom of the enclosure. The horizontal ducts shall communicate directly with the outdoors. See Figure 12.

Each duct opening shall have a minimum free area of 1 square inch per 2,000 Btu/hr (1100 mm2 per kW) of the aggregate input rating of all appliances installed in the enclosure.

When ducts are used, they shall be of the same cross sectional area as the free area of the openings to which they connect. The minimum dimension of rectangular air ducts shall be not less than 3 inches.

19

Image 19
Contents Commercial gas water heaters Table Of Contents Approvals Safe Installation, Use and ServiceOverheated water can cause water tank explosion General Safety InformationPrecautions Hydrogen Gas FlammableFire or Explosion Hazard Installing, using or servicing Water heaterFire and Explosion Hazard Qualifications Preparing For The InstallationIntroduction Abbreviations UsedBasic Operation Features And ComponentsTop Views 120,000 & 150,000 Water Heater’s 120 VAC on/off switchSUF 120 & 150 Components SUF 199 & 250 Components Top ViewsWater heaters 24 Volt Gas Valve Left Side Right Side Rough In Dimensions Installation ConsiderationsTOP Views Storage Capacities Recovery CapacitiesLocating The Water Heater Gas Line Connection SizeCirculation Pumps Extended Vent TerminationsOptional Concentric Terminations Hard WaterSupply Gas Line Installation RequirementsPower Supply Gas Pressure RequirementsThermal Expansion Mixing ValvesDishwashing Machines Closed Water SystemsWater Damage Hazard Temperature-Pressure Relief ValveValve Discharge Pipe Requirements Condensate Drain Water Trap Condensate DrainCombustible Material Storage Contaminated AirConfined Space Breathing Hazard Carbon Monoxide GasAir Requirements Unconfined SpaceOutdoor Air Through Two Horizontal Ducts Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through One OpeningPage Inspection Commonwealth of MassachusettsGeneral Venting Information Venting InstallationGeneral Venting Instructions TEE Fitting SUF 199 & SUF 250 Intake Air ConnectionCorrect Orientation Large Hose Fernco ClampVenting Requirements Power Vent Installation Venting Installation SequenceDirect Vent Installation Field Supplied Intake AIR ScreenStandard Factory Supplied Terminations Vertical Termination InstallationField Supplied STRAP/SUPPORT Maximum Factory Supplied Standard TerminationIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Determine the location for the termination Concentric Termination InstallationInch Concentric Termination KIT Inch Concentric Termination InstallationEight Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Four Concentric TerminationsSidewall Roof Multiple Concentric Termination ArrangementsTwo Concentric Terminations Eight Concentric TerminationsVenting Arrangements Power Vent HorizontalDirect Vent Horizontal Direct Vent Horizontal Vent Vertical Intake Direct Vent Vertical Vent Horizontal IntakeDirect Vent Horizontal Concentric Power Vent Termination Clearances Sidewall Power VentDirect Vent Termination Clearances Sidewall Direct VentInstallation Instructions Water Heater InstallationCondensate Drain Installation Installation NotesSupply Gas Line Sizing Metric Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing U. S. UnitsGas Line Leak Testing Supply Gas Regulator InstallationGas Line Connection Connecting An External Supervisory Control Electrical WiringPower Supply Connections Enable/Disable CircuitThermometers not Supplied Water Piping DiagramsWater Line Connections Valve Discharge PipeThermostat Control Temperature RegulationHigh Temperature Limit Control ECO High Temperature ApplicationsControl System Navigation Tank Temperature 103F Operating Set Point 120FControl System Operation OverviewIcon Description Status IconsMenu Description Operating StatesState Description Control System MenusDescription/Action Display User Settings & Control System MenusUpdate Cancel Back HelpChange Back Help Heater Information Description/Action Display Display Settings Description/ActionYES Back AdvancedView Back Help ECOName UpdateService Contact Information Select Back HelpPrior to Start up Start UpInitial Start Up Gas pressure reading while the water heater is firing GAS Valve / Venturi Assembly TOP ViewGAS Valve TOP Detail View Lighting The Water HeaterMultiple Appliance Installations To Turn Off Gas High Altitude InstallationsChecking The Firing Rate 1050 = 300,000 Btu/hr 87.9 kWSUF 60 120 and SUF 100 150 Models only Lighting The Water HeaterLighting & Operation Labels SUF 100 199 and SUF 100 250 Models only Tank Temperature 103F Operating Set Point 120FInstallation Checklist TroubleshootingSequence Of Operation Closed by control system Fault Msg is displayed Sequence Of Operation Flow ChartPre-Purge cycle Momentary Ignition Operational ProblemsInstallation Errors Rough Starting, Rough OperationFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesBack Advanced No Anode Voltage Blower Prover FailureDraining And Flushing MaintenanceMaintenance Schedule GeneralManual Lime Scale Removal Filling The Water HeaterSediment Removal Lime Scale RemovalVent System Powered Anode RodsDrain Valve and Access Panels Temperature-Pressure Relief Valve TestCCB Central Control Board Layout DiagramsJ3 J5 J10 J13 J11User Interface Modul SUF 120 & 150 Wiring DiagramCCB Central Control Board SUF 199 & 250 Wiring DiagramCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty