Concentric Termination Installation

1.Concentric terminations must be ordered separately. SUF 100 120 - 250 models must use the 4 inch concentric termination; Part Number: 9006328005. Contact your local distributor or call the parts department phone number on the back cover of this manual to order concentric terminations.

2.Determine the location for the termination.

Note: Roof termination is preferred since it is less susceptible to damage, has reduced chances to intake contaminants and vent vapors are less visible.

3.When installing a concentric termination vertically through the roof; ensure that all exterior vertical clearance requirements for the concentric termination, shown in Figure 30 on page 31 are being maintained. These clearances and those cited by local and national codes must be maintained.

4.When installing a concentric termination vertically through a flat roof, the termination's vent cap must be a minimum of 10 feet (3 m) away from any parapet, vertical wall or structure as shown in Figure 28.

CONCENTRIC TERMINATION(S) MUST BE A MINIMUM OF 10 FEET (3 m) AWAY FROM ANY PARAPET, VERTICAL WALL OR STRUCTURE.

4 INCH CONCENTRIC TERMINATION

FLAT ROOF CLEARANCE

Figure 28

Note: If this required 10 foot (3 m) distance to a parapet, vertical wall or structure cannot be maintained, standard terminations must be used. See Vertical Termination Installation on page 27.

5.When installing a concentric termination through a sidewall; ensure that all exterior sidewall clearance requirements for the termination, shown in Figure 49 on page 37, are being maintained. These clearances and those cited by local and national codes must be maintained.

6.When installing multiple concentric terminations vertically through a roof or horizontally through a sidewall ensure the required clearances between terminations and groupings of multiple terminations are maintained. See pages 32 and 33 for more information.

7.Cut a 5 inch (13 cm) diameter hole for the 4 inch concentric termination where the termination will pass through the wall or roof.

Note: Beware of concealed wiring and piping when cutting through the wall or roof.

8.When installing multiple concentric terminations vertically through the roof in the same location the termination caps for all concentric terminations must be at the same height measured from ground. See Multiple Concentric Termination

Arrangements on page 33.

9.Determine if the concentric termination will need to be shortened or lengthened to accommodate required clearances or to ensure all vent caps are at the same height when installing multiple terminations vertically through the roof in the same location.

See Figure 29 on page 31 for the maximum and minimum lengths allowed for the 4 inch concentric termination.

When extending the length of a concentric termination do not use couplings. The use of couplings will restrict flow through the termination and may cause improper combustion. The termination’s intake air and vent pipes must be replaced with longer sections of the same pipe material when extending the length of the termination.

Use only SDR-26 pipe to extend the 4 inch concentric termination.

When shortening the length of the termination carefully measure and cut the larger (intake air) pipe first. Cut the same amount of pipe off of the smaller (vent) pipe.

10.Proceed to 4 Inch Concentric Termination Installation on page 31.

30

Image 30
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ApprovalsHydrogen Gas Flammable General Safety InformationPrecautions Overheated water can cause water tank explosionInstalling, using or servicing Water heater Fire or Explosion HazardFire and Explosion Hazard Abbreviations Used Preparing For The InstallationIntroduction QualificationsFeatures And Components Basic OperationWater Heater’s 120 VAC on/off switch Top Views 120,000 & 150,000SUF 120 & 150 Components Top Views SUF 199 & 250 ComponentsWater heaters 24 Volt Gas Valve Left Side Right Side Installation Considerations Rough In DimensionsTOP Views Gas Line Connection Size Recovery CapacitiesLocating The Water Heater Storage CapacitiesHard Water Extended Vent TerminationsOptional Concentric Terminations Circulation PumpsGas Pressure Requirements Installation RequirementsPower Supply Supply Gas LineClosed Water Systems Mixing ValvesDishwashing Machines Thermal ExpansionTemperature-Pressure Relief Valve Water Damage HazardValve Discharge Pipe Requirements Contaminated Air Condensate DrainCombustible Material Storage Condensate Drain Water TrapUnconfined Space Breathing Hazard Carbon Monoxide GasAir Requirements Confined SpaceOutdoor Air Through One Opening Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionVenting Installation General Venting InformationGeneral Venting Instructions Large Hose Fernco Clamp SUF 199 & SUF 250 Intake Air ConnectionCorrect Orientation TEE FittingVenting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation Intake AIR Screen Field SuppliedVertical Termination Installation Standard Factory Supplied TerminationsMaximum Factory Supplied Standard Termination Field Supplied STRAP/SUPPORTIntake AIR AND/OR Vent Exhaust Sidewall Termination Installation Concentric Termination Installation Determine the location for the terminationInch Concentric Termination Installation Inch Concentric Termination KITFour Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Eight Concentric TerminationsEight Concentric Terminations Multiple Concentric Termination ArrangementsTwo Concentric Terminations Sidewall RoofPower Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentInstallation Notes Water Heater InstallationCondensate Drain Installation Installation InstructionsSupply Gas Line Sizing U. S. Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing Metric UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Enable/Disable Circuit Electrical WiringPower Supply Connections Connecting An External Supervisory ControlValve Discharge Pipe Water Piping DiagramsWater Line Connections Thermometers not SuppliedHigh Temperature Applications Temperature RegulationHigh Temperature Limit Control ECO Thermostat ControlOverview Tank Temperature 103F Operating Set Point 120FControl System Operation Control System NavigationStatus Icons Icon DescriptionControl System Menus Operating StatesState Description Menu DescriptionBack Help User Settings & Control System MenusUpdate Cancel Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayECO Back AdvancedView Back Help YESSelect Back Help UpdateService Contact Information NameStart Up Prior to Start upInitial Start Up Lighting The Water Heater GAS Valve / Venturi Assembly TOP ViewGAS Valve TOP Detail View Gas pressure reading while the water heater is firingMultiple Appliance Installations 1050 = 300,000 Btu/hr 87.9 kW High Altitude InstallationsChecking The Firing Rate To Turn Off GasLighting The Water Heater SUF 60 120 and SUF 100 150 Models onlyLighting & Operation Labels Tank Temperature 103F Operating Set Point 120F SUF 100 199 and SUF 100 250 Models onlyTroubleshooting Installation ChecklistSequence Of Operation Sequence Of Operation Flow Chart Closed by control system Fault Msg is displayedPre-Purge cycle Rough Starting, Rough Operation Operational ProblemsInstallation Errors Momentary IgnitionFault And Alert Conditions Fault And Alert Messages Possible Causes Check/Repair Displayed Fault/Alert MessageBack Advanced Blower Prover Failure No Anode VoltageGeneral MaintenanceMaintenance Schedule Draining And FlushingLime Scale Removal Filling The Water HeaterSediment Removal Manual Lime Scale RemovalTemperature-Pressure Relief Valve Test Powered Anode RodsDrain Valve and Access Panels Vent SystemJ10 J13 J11 DiagramsJ3 J5 CCB Central Control Board LayoutSUF 120 & 150 Wiring Diagram User Interface ModulSUF 199 & 250 Wiring Diagram CCB Central Control BoardCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty