Appendix G-2 Turbine Installation QA Checklist

153

Tip Brake Installation

Ensure tip brake slides into blade end without obstruction Tip brake cables properly attached to connector points Ensure installation of low-profile washers

Torque 5/16 mounting nuts to 11 ft/lbs

Torque 3/8" studs to 18 ft/lbs

Perform tip brake pull test

Check

Assy by

Q.A.

Date

 

 

 

Installing Turbine

Check

Tower top bolts torqued to 600 ft/lbs

Confirm free yaw with yaw lock disengaged

Install twist cables into twist cable junction box

Install anemometer assembly at proscribed location on tower

Assy by

Q.A.

Date

 

 

 

QA approval signature

Date