AOC 15 user manual Generator Test

Models: 15

1 241
Download 241 pages 40.58 Kb
Page 71
Image 71

8.0 Function Tests and Commissioning

63

Test emergency shut down (See Section 9.3.8)

Test low wind shut down (See Section 9.3.9)

It is a good idea to observe the wind turbine running under normal conditions to verify its correct operation. After it has been observed in normal winds, it may be signed off and formally commissioned.

8.2 Generator Test

Each generator should be run briefly to determine proper phase rotation. The test can be carried out during commissioning by rotor jogging the wind turbine briefly and observing the rotation of the main shaft. If the phase rotation is correct the turbine will rotate counter clockwise when looking upwind. If the direction of rotation is incorrect, any two of the phase leads should be changed over and the test repeated. The only wires to be changed in the control box are the phase leads to the turbine, TB2.

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.

DOC012R02

AOC 15/50 User Manual

Nov 2001

Page 71
Image 71
AOC 15 user manual Generator Test