6.0 Tower and Wind Turbine Generator Installation | 45 |
aligned properly and be seated completely in the slot counter bore of the hub. If a washer becomes misaligned while torque is applied, the bolt must be loosened and the washer realigned.
For the attachment of the second blade, the hub is rotated so that the blade can be mounted with its tip supported, as was done for the first blade. The first blade will need to be supported initially by slings attached to a boom truck or crane. Once the hub is in the correct position the parking brake can be applied and the boom truck released. The procedure for mounting and aligning the second blade is as for the first one. The procedure for attaching the third blade is described in the Section 6.5.
+2.3°
0°
1
9
Figure 6-9 Pitch adjustment
4 | 7 | 2 |
| ||
|
|
6 | 8 |
3 |
Figure 6-10 Blade Torque Pattern
10
5
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.
DOC012R02 | AOC 15/50 User Manual | Nov 2001 |