9.0 Wind Turbine Operation | 78 |
Emergency Stop Pushed In:
The emergency stop switch overrides all other switches. With the emergency stop pushed in, the wind turbine should come to a complete stop and
Emergency Stop Pulled Out:
With the emergency stop switch pulled out, all the other switches can be operated.
9.3Test Operation
The following sections show the procedures used when testing the wind turbine functions after installation and/or after any maintenance has been performed.
Before placing the wind turbine into service for the first time and after any maintenance and/or repair work, the following tests must be carried out and the commissioning/checkout test sheet (see Appendix G) must be completed.
9.3.1Power Up
1.Set all control switches to OFF.
2.Open the three 15 Amp circuit breakers on the 120 V side of the control transformer (1CB, 2CB, 3CB).
3.Open the
4.Energize the 480 V bus from the utility network.
5.Close the three pole, 3 Amp breakers to energize the control transformer (4CB, 5CB, 6CB).
6.Check for 120 VAC output on the control transformer.
7.Close the three 15 Amp circuit breakers on 120 V side of the control transformer (1CB, 2CB, 3CB).
8.Observe the panel lights, which should run through a flash sequence after which the turbine ready light should light up and remain on.
9.3.2Parking Brake Release Test
1.Set the turbine test switch to TEST.
2.Set the parking brake release switch to ON.
3.Observe the rotor movement.
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.
DOC012R02 | AOC 15/50 User Manual | Nov 2001 |