6.0 Tower and Wind Turbine Generator Installation | 39 |
CAUTION
THE BLADES SHOULD NOT BE SCRATCHED OR GOUGED
DURING SITE HANDLING AS THIS CAN CAUSE A LOSS OF
ROTOR PERFORMANCE AND/OR BLADE DEGRADATION
FROM ENVIRONMENTAL EFFECTS.
The string in the conduit should be used to pull a #10 gage wire through the conduit. The blade cable should then be attached to the wire (with tape, for example) and pulled through the blade conduit, with the molded
To avoid damaging the tip brakes during blade installation, it is preferable to install them once the blades have been attached to the hub. Till then, the blade ends should be protected with foam to prevent damage, should they strike the ground or any hard object.
After connecting the electromagnet, the tip brake assembly should be inserted carefully into the end of the blade without pinching the electromagnet wires. Each tip brake should be bolted to its blade using low profile
CAUTION
FORCING THE TIP BRAKE INTO THE BLADE CAVITY CAN
DAMAGE BOTH THE BLADE AND THE TIP BRAKE. TIP
BRAKES SHOULD SLIDE INTO THE BLADE CAVITY
EASILY.
After the tip brake has been mounted on the blade and wired, the blade should be positioned so that the tip brake can open and close freely. The tip brake should be opened and let go; it should close completely.