6.0 Tower and Wind Turbine Generator Installation | 47 |
before hoisting the wind turbine generator will make alignment with the tower easier. The timing of yaw lock release should be determined by trained personnel.
Photo Courtesy of
KEA
Figure 6-12 Lifting of tilt down tower at Kotzebue Electric Association
The large crane should lift the wind turbine generator using two slings as shown in Figure
THE WIND TURBINE GENERATOR!
CAUTION
ALL LIFTING DEVICES SHOULD BE INSPECTED FOR
INTEGRITY, SUITABILITY FOR PURPOSE AND CORRECT
ATTACHMENT BEFORE LIFTING.
The wind turbine generator should be lifted slightly to see whether it sits level in its slings. If it does it should be lowered back to the ground and its slings readjusted.
The wind turbine generator should be lifted slowly to a height of approximately 4 m (13 feet), while the blade closest to the ground is held steady and rotate until it is directly vertical. The parking brake needs to be released. The third blade can now be mounted to the hub with the
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.