4.0 Planning and Installation Checklist

27

4.6Electrical Planning Considerations

The local wiring inspector should review the design of the electrical installation before work starts at the site. The following items should be considered in the design/installation of the electrical system:

∙Wire sizes, length and type as described in Appendix M

∙Conduit type and size

∙Service entrance hardware

∙Revenue meter specifications

∙Protective hardware required by the interfacing utility

∙Distribution panel(s) with properly sized circuit protection

∙Single phase power for control house lights and receptacles

∙Step down transformer characteristics

∙Control house interior wire ways

∙Control house junction box(es)

∙Multiple unit control for wind power stations

∙Twist cable termination box

∙Foundation/conduit interfaces

4.7Installation Tools and Equipment

The installation of the AOC 15/50 requires specific tools and equipment (see Appendix I). Below is a breakdown of steps to take or equipment to have on hand for the three main installation phases.

For tower assembly:

∙Tower manufacturer’s assembly drawings

∙Checklist of tower parts, hardware and tools

∙Torque specifications

∙Tripod, bucket, backhoe or boom truck

∙Personnel for lifting and assembly

∙Anemometer boom and brackets

To prepare machine:

∙If wind turbine generator was shipped in a crate, remove from crate

∙Check components

∙Open blade crate

For installation:

∙Slings, ropes, buckets and tools

∙Adequately trained personnel

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.

DOC012R02

AOC 15/50 User Manual

Nov 2001

Page 35
Image 35
AOC 15 user manual Electrical Planning Considerations, Installation Tools and Equipment