AOC 15 Installation Personnel Considerations, General Installation/Commissioning Timeline

Models: 15

1 241
Download 241 pages 40.58 Kb
Page 36
Image 36

4.0 Planning and Installation Checklist

28

Platform or bucket for blade installation

Appropriate safety equipment

Crane

Forklift or boom truck

4.8Installation Personnel Considerations

The installation and maintenance of a wind turbine requires specialized skills, equipment and experience. AOC assumes that all installation and operation personnel will have these skills, experience and equipment. Only trained and qualified technicians should attempt to climb a wind turbine tower and should use OSHA/ANSI approved practice and equipment. It is highly recommended that a trained AOC representative be present for the erection and assembly of the wind turbine (see Section 4.9). The following personnel should also be present, as and when required, during installation:

One to two qualified technicians trained in climbing safety to erect and install wind turbine

Qualified crane operator to operate the crane during tower and wind turbine lifting

Certified electrician and/or utility personnel to install cables and wire controllers

Additional labor for non-technical tasks such as tower assembly

4.9General Installation/Commissioning Timeline

The following timeline represents the minimum installation schedule for one wind turbine under ideal circumstances. Three to five days is usually a reasonable estimate. Poor weather conditions, logistic problems and poor planning may extend the timeline considerably.

Site Preparations and Construction:

Pour foundation

Create cableways, wiring, power cables

Install and wire control boxes, capacitor, and dynamic brakes

Inspect wind turbine and hardware

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this document.

DOC012R02

AOC 15/50 User Manual

Nov 2001

Page 36
Image 36
AOC 15 user manual Installation Personnel Considerations, General Installation/Commissioning Timeline