4.0 Planning and Installation Checklist

29

Day 1:

∙Plan and prepare erection

∙Assemble tower

∙Test generator and use it as a motor to test drive train

∙Clean blades and install tip brake cable

∙Prepare tip brake studs and cavity

∙Prepare blade bolt inserts

∙Attach twist cable

∙Install two of three blades if time permits (fork lift, boom truck, etc.)

Day 2:

∙Lift and install tower on foundation (crane)

∙Install blades on hub

∙Install tip brakes on blade ends

∙Lift and mount machine onto the tower

∙Torque tower top fasteners

∙Torque all tower bolts and add pal nuts

Day 3:

∙Install and wire anemometers

∙Wire twist cable junction box and disconnect (if applicable) at tower base

∙Grout tower legs

∙Mount warning signs as required

∙Troubleshoot and commission

Day 4:

∙Complete any further installation details

∙Carry out final QA check

∙Monitor performance (wind permitting)